INSP-Final Inspection | 4/8/2008 | 4/8/2008 | 4/8/2008 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Supply line flush | 1/8/2008 | 1/9/2008 | 1/9/2008 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 11/27/2007 | 11/27/2007 | 11/27/2007 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
|
INSP-Sprinkler Rough-in | 11/13/2007 | 11/13/2007 | 11/13/2007 | P | PASS |
Troy Cobbley
|
|
|
The underground tie in to the United Water line is complete and ok to bury.
|
INSP-Supply line flush | 10/24/2007 | 10/24/2007 | 10/24/2007 | P | FAIL |
Troy Cobbley
|
|
|
The inspection was called in for a flush but what was actually needed was a cover inspection for the 8" underground supply. The underground piping is ok to cover.
|
Sprinkler Plan Check | 10/8/2007 | | 10/8/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/8/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/8/2007 | | 10/8/2007 | | DONE |
|
|
|
|
Telephone call | | | 10/8/2007 | | DONE |
|
|
|
tlk to jeff t anderson ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 10/8/2007 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/8/2007 | | DONE |
|
|
|
|
Application received | | | 10/3/2007 | | |
|
|
|
|
Pending Assignment by SAM | 10/3/2007 | | | | |
|
|
|
|