INSP-Final Inspection | 12/15/2010 | 12/16/2010 | 12/16/2010 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
FIR-Aging Inspection | 12/2/2010 | 12/2/2010 | 12/7/2010 | | NR |
Troy Cobbley
|
|
|
This permit and the building permit information have been forwarded to Scott and Jennifer after the owner contacted Jennifer for an extension of a temporary occupancy.
|
FIR-Aging Inspection | 7/2/2010 | 7/2/2010 | 7/6/2010 | | NR |
Troy Cobbley
|
|
|
Per Mike the tenant is waiting for funding to finish this project.
|
INSP-Conference | 4/22/2010 | 4/23/2010 | 4/23/2010 | A | DONE |
Troy Cobbley
|
|
|
I stopped at the job site and found that the restroom has been installed and stairs have been installed to the mezzanine both are lacking sprinkler protection. I spoke to Mike about getting the permit finished.
|
Miscellaneous action | | | 3/10/2010 | | DONE |
|
|
|
Sent email requesting project status.
|
INSP-Final Inspection | 12/3/2007 | 12/4/2007 | 12/4/2007 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with dave hannimans permission until the restroom in the vault is complete and the mezzanine is complete.
|
Inspection Record Card- Fire | 11/29/2007 | | 11/29/2007 | | DONE |
|
|
|
|
Telephone call | | | 11/29/2007 | | DONE |
|
|
|
left vm for mike oswald at ###-#### - permit ready and no fee due (plan modification)
|
Permit Ready to Issue | | | 11/29/2007 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/29/2007 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/28/2007 | | |
|
|
|
Received three applications and submittal packetts; taken to fire review
|
(F) Reprint permit | | | 11/28/2007 | | DONE |
|
|
|
|
Telephone call | | | 11/28/2007 | | DONE |
|
|
|
I called Absolute FP (Sam Ball) regarding the plan modification they just submitted. We will handle on a quick permit basis. They are planning to start and finish the work on Monday 12/3 so the sprinkler and building inspections should be able to be done morning of 12/4 in time to get the CO that afternoon, so they can open 12/5. I called Mollie Winger, (owner, ###-####) advised that Absolute FP has submitted a Quick Permit application to sprinkler the vault, plus a rest room and stairs that were also added. I outlined the steps to get the sprinkler, fire/life safety and building inspections scheduled for Tuesday morning so she can bring in the card and get her CO that afternoon. She will try to get Absolute to do the work on Friday, so she isn't in such a time crunch on Tuesday.
|
Sprinkler Plan Check | 11/28/2007 | | 11/28/2007 | | PASS |
Scott Arellano
|
|
|
Attached sprinkler plans and application in documents.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/28/2007 | | DONE |
|
|
|
|
Telephone call | | | 11/26/2007 | | DONE |
|
|
|
Telcon from Mollie Wingert, owner, regarding lack of sprinklers in new vault she had constructed to store donated computers until the hard drives are cleaned; donors require the vault for security of their donated computers until drives are erased. She was told by her architect that sprinklers were not required, therefore the room was not included or shown on the sprinkler plans. Room is approx 900 sf, storage will be computers on shelves or racks to 5 ft high. I confirmed T. Cobbly's field decision that sprinlers are required. She has Absolute FP scheduled to come out this afternoon to submit a new plan for the room; I confirmed this would be a Quick permit and we can review it within 24 hrs so she may still be able to meet her advertised opening of 12/5. Invited her to call me if she runs into any problems.
|
INSP-Sprinkler Rough-in | 10/12/2007 | 10/12/2007 | 10/12/2007 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping is ok to cover. The single head in the storage room is to be lowered so that it will provide coverage under the duct work.
|
Sprinkler Plan Check | 10/10/2007 | | 10/10/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/10/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/10/2007 | | 10/10/2007 | | DONE |
|
|
|
|
Telephone call | | | 10/10/2007 | | DONE |
|
|
|
left vm for mike oswald at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 10/10/2007 | | DONE |
|
|
|
|
Issue permit | | | 10/10/2007 | | DONE |
|
|
|
|
Case Summary | | | 10/9/2007 | | |
|
|
|
|
Application received | | | 10/9/2007 | | |
|
|
|
|
Pending Assignment by SAM | 10/9/2007 | | | | |
|
|
|
|