INSP-Final Inspection | 4/28/2009 | 4/28/2009 | 4/28/2009 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 4/27/2009 | 4/28/2009 | 4/28/2009 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 4/6/2009 | 4/7/2009 | 4/7/2009 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where the sprinkler piping can be covered. It will have todays date.
|
INSP-Sprinkler Rough-in/Hydro | 3/16/2009 | 3/17/2009 | 3/17/2009 | A | PASS |
Troy Cobbley
|
|
|
Above ground hydro test for ALF canopy on the south side of the building passed.
|
INSP-Sprinkler Rough-in | 3/2/2009 | 3/3/2009 | 3/3/2009 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the canopy on the southwest corner of the building where the piping is ok to cover.
|
INSP-Final Inspection | 12/11/2008 | 12/12/2008 | 12/12/2008 | P | PART |
Troy Cobbley
|
|
|
The new Dining Room and the Aid Station areas sprinkler system is complete.
|
INSP-Sprinkler Rough-in/Hydro | 11/20/2008 | 11/21/2008 | 11/21/2008 | A | FAIL |
Forrest France
|
|
|
Inspection for the aid station room only passed as initialed and red lined on plans, also noted one overspaced head and one obstructed head at the adjacent common corridor-see red line annotations.
|
INSP-Final Inspection | 11/20/2008 | 11/20/2008 | 11/20/2008 | P | NH |
Forrest France
|
|
|
No access to complete inspection.
|
INSP-Sprinkler Rough-in | 11/3/2008 | 11/4/2008 | 11/4/2008 | A | PART |
Troy Cobbley
|
|
|
The above ground hydro test for the new dining room passed and the piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 10/31/2008 | 11/3/2008 | 11/3/2008 | P | FAIL |
Troy Cobbley
|
|
|
steven Phone #: ###-#### The contact phone number is wrong so I went to the job site and did not make contact in person. I called the field supervisor todd but could only leave a message on voice mail. Also the plans at the pipe machine are not the city approved. No inspection was performed and will need to be rescheduled.
|
INSP-Sprinkler Rough-in | 10/28/2008 | 10/29/2008 | 10/29/2008 | P | PART |
Forrest France
|
|
|
The overhead install at the dining area appears acceptable however pipe sizing does not match approved plan set on site, contractor to provide stamped drawings reflecting the accurate sizing prior to approval for cover, relocated heads at the existing corridors okayed with the exception of one overspaced head and one armover missing a hanger.
|
INSP-Sprinkler Rough-in | 10/21/2008 | 10/22/2008 | 10/22/2008 | P | PART |
Troy Cobbley
|
|
|
No approved plans were presented but I gave approval to cover the piping in the narrow soffict in the new dining room.
|
INSP-Sprinkler Rough-in | 6/26/2008 | 6/27/2008 | 6/27/2008 | P | CANC |
Forrest France
|
|
|
james Note: cover up Phone #: ###-#### Inspection cancelled from web by: Alexandra Rahn
|
INSP-Sprinkler Rough-in | 6/19/2008 | 6/20/2008 | 6/20/2008 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the sprinkler piping in the one overbuild that is ok for cover. The connection into the existing dry system is not complete and has been marked as such on the plans.
|
INSP-Final Inspection | 6/17/2008 | 6/19/2008 | 6/19/2008 | A | PART |
Troy Cobbley
|
|
|
The fire sprinkler work for the two room west addition and the ten room west addition is complete. 401 canopies have been added at al of the heads that were in conflict with the lights. Jim is to provide 401 canopies for the two pendants that were in the locked closets and change the sidewall heads in the corridor ceiling pockets to quick responce. I will verify this work at the next inspection. Also the sprinkler piping in the connecting corridor, as marked on the approved plans, is ok to cover. This piping has not been connected to the dry system yet and will need to be verified at a later time.
|
Plan assigned to (SAM) | 5/21/2008 | | 6/13/2008 | | PASS |
Cathy Brown
|
|
|
6/13/2008 10:01:59 CMB - activity updated through activity FIRA22 from case FIR07-00874.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/13/2008 | | DONE |
Cathy Brown
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Inspection Record Card- Fire | 6/13/2008 | | 6/13/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 6/13/2008 | | DONE |
|
|
|
t/c w tyson smith at ###-#### - permit ready and fees given
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Permit Ready to Issue | | | 6/13/2008 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Issue and Print Permit | | | 6/13/2008 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 6/9/2008 | 6/10/2008 | 6/10/2008 | A | DONE |
Troy Cobbley
|
|
|
This inspection was actually for a conference regarding the light fixtures blocking the pendant sprinkler spray. Grinnell did not show up for the conference but the superintendant for Petra was there and he made a copy of the Beam Rule spacing chart in NFPA 13 cahpter 8. We measured a couple of heads so that he knew what I was looking at.
|
Sprinkler Plan Check | 5/21/2008 | | 6/10/2008 | | PASS |
|
|
|
Plans are approved with Conditions by Bryan Johnson
|
Override - Parcel Holds | | | 6/9/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/9/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/9/2008 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 6/6/2008 | 6/6/2008 | 6/6/2008 | P | PASS |
Troy Cobbley
|
|
|
24 hour air test for the Dining Area and the Aid Station has passed
|
Override - Parcel Holds | | | 6/6/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/6/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/6/2008 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 6/4/2008 | 6/5/2008 | 6/5/2008 | A | PART |
Troy Cobbley
|
|
|
The 24 hour air tests have been started for the Aid Station with 42psi on the guage and the Dining Area with 47psi on the guage. Test started at 9:00am
|
INSP-Sprinkler Rough-in/Hydro | 6/3/2008 | 6/4/2008 | 6/4/2008 | P | PASS |
Troy Cobbley
|
|
|
The dry system hydro test for the Aid Station and the Dining area passed.
|
Override - Parcel Holds | | | 6/4/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/4/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/4/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/3/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/3/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/3/2008 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 5/28/2008 | 5/30/2008 | 5/30/2008 | A | PART |
Troy Cobbley
|
|
|
The 24 hour air test on the ALF passed but it failed on the Nurses Station.
|
INSP-Sprinkler Rough-in/Hydro | 5/28/2008 | 5/29/2008 | 5/29/2008 | A | DONE |
Troy Cobbley
|
|
|
The 24 hour air test was begun with 42psi on both the ALF and the Nurses Station dry systems at 8:15am. It also appears that many of the pendant heads do not meet the three times rule from the light fixtures.
|
INSP-Sprinkler Rough-in/Hydro | 5/28/2008 | 5/28/2008 | 5/28/2008 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro test of the ALF dry system passed.
|
Override - Parcel Holds | | | 5/28/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 5/28/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 5/28/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 5/28/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 5/28/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 5/28/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 5/28/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 5/28/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 5/28/2008 | | |
|
|
|
|
(F) Reprint permit | | | 5/21/2008 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/21/2008 | | |
|
|
|
Plan Modification: Received letter and four copies of application, United Water Flow sheet, hydraulic calculations, product data, and sheets FP1, FP2, FP3; taken to fire review
|
INSP-Sprinkler Rough-in | 5/19/2008 | 5/20/2008 | 5/20/2008 | A | PASS |
Troy Cobbley
|
|
|
The AOF dining area dry system is ok to cover.
|
Override - Parcel Holds | | | 5/19/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 5/19/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 5/19/2008 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 5/13/2008 | 5/14/2008 | 5/14/2008 | P | CANC |
Troy Cobbley
|
|
|
Per stephen the dry system hydro test failed due to a dry pendant. Will be rescheduled.
|
INSP-Sprinkler Rough-in/Hydro | 5/12/2008 | 5/13/2008 | 5/13/2008 | A | PASS |
Troy Cobbley
|
|
|
The 24 hour air test on the west dry system passed.
|
Override - Parcel Holds | | | 5/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 5/13/2008 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 5/9/2008 | 5/12/2008 | 5/12/2008 | A | PART |
Troy Cobbley
|
|
|
The east wet system hydro test passed. The west wet system hydro test passed. The west dry system 24 hour air test was started at 9:30. I took two time to pass the hydro tests today.
|
Override - Parcel Holds | | | 5/12/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 5/12/2008 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 5/7/2008 | 5/9/2008 | 5/9/2008 | A | PART |
Troy Cobbley
|
|
|
The hydro test of the south wing dry system passed. The hydro test of the south wing wet system failed.
|
Override - Parcel Holds | | | 5/7/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 5/7/2008 | | |
|
|
|
AOF area
|
INSP-Sprinkler Rough-in | 1/31/2008 | 2/1/2008 | 2/1/2008 | A | PASS |
Troy Cobbley
|
|
|
The piping rough-in for the wet and dry systems in the new northwest wing are passed. The tenting of the pipe is not complete. No piping can be covered yet.
|
Override - Parcel Holds | | | 1/31/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 1/31/2008 | | |
|
|
|
|
INSP-Sprinkler Rough-in | 1/30/2008 | 1/30/2008 | 1/30/2008 | P | PASS |
Troy Cobbley
|
|
|
The tenting/insulation for the south wing is acceptable. Piping still can not be covered since the stop work order for the fire alarm system still stands.
|
INSP-Sprinkler Rough-in | 1/28/2008 | 1/29/2008 | 1/29/2008 | P | PART |
Troy Cobbley
|
|
|
The rough-in for the piping in the south wing matches the as-built plans except for the two starter pieces for the branchlines at the building connection. Plans indicate 2" starter pieces but the size installed is 1 1/2". The tenting is not complete yet.
|
INSP-Sprinkler Rough-in | 1/24/2008 | 1/25/2008 | 1/25/2008 | P | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for the wet system. I failed it because the plans and hydraulic calculations state the max spacing is to be 196sq ft per head. The installation and the piping plans show the heads at nearly 225sq. ft. I contacted Brian. The plans need to be resubmitted prior to the next inspection for verification that the greater spacing is hydraulically supported.
|
INSP-Sprinkler Rough-in | 1/22/2008 | 1/24/2008 | 1/24/2008 | P | FAIL |
Troy Cobbley
|
|
|
I arrived at the job site and was notified that the project was not ready for my re-inspection.
|
Override - Parcel Holds | | | 1/24/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 1/24/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 1/22/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 1/22/2008 | | |
|
|
|
|
INSP-Sprinkler Rough-in | 1/15/2008 | 1/18/2008 | 1/18/2008 | P | PART |
Troy Cobbley
|
|
|
The attic system rough-in in the south wing is passed. Per jim and I's discussion it will be ok to provide a 1" drain from the 2 1/2" branchline to the 4" main. Through bolts are required on all of the earthquake attachments. The dry piping in the overbuilds has not been installed yet nor has the 4" tie in.
|
Override - Parcel Holds | 1/15/2008 | 1/1/1900 | 1/15/2008 | | |
|
|
|
nothing to do with modification
|
Issue and Print Permit | | | 12/26/2007 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/21/2007 | | DONE |
|
|
|
|
Telephone call | | | 12/21/2007 | | DONE |
|
|
|
lft vm with tyson smith ###-#### that permit and fees are ready to be picked up
|
Inspection Record Card- Fire | 12/21/2007 | | 12/21/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/21/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/28/2007 | | 12/18/2007 | | PASS |
|
|
|
Plans are approved with conditions by Bryan Johnson
|
Plan resubmittals received | | | 11/28/2007 | | |
|
|
|
received "5" applications & "5" sets of plans- put plans on fire shelf
|
Application received | | | 10/18/2007 | | |
|
|
|
|
Case Summary | | | 10/18/2007 | | |
|
|
|
|
Sprinkler Plan Check | 10/31/2007 | | | | FAIL |
|
|
|
These plans were denied due to lack of detail and discrepancies with general notes.
Upon request, these plans may be retrieved from my office for salvage. The denied set will be maintained for five working days.
|
Pending Assignment by SAM | 10/18/2007 | | | | |
|
|
|
|