INSP-Final Inspection | 7/17/2008 | 7/17/2008 | 7/17/2008 | P | PASS |
Forrest France
|
|
|
Noted correction items are complete, fire sprinkler permit finaled.
|
INSP-Supply line flush | 7/16/2008 | 7/17/2008 | 7/17/2008 | P | DEFR |
Forrest France
|
|
|
Duplicate inspection request-flush completed, final inspection scheduled.
|
INSP-Final Inspection | 7/16/2008 | 7/16/2008 | 7/16/2008 | P | FAIL |
Troy Cobbley
|
|
|
Surface mounted lights in both of the first floor and second floor janitor closets and the second floor elevator room are blocking the sprinkler pendants. Also the riser room is required to be one hour rated but has holes and a block out for a ceiling mounted access panel.
|
INSP-Alarm Testing | 7/15/2008 | 7/16/2008 | 7/16/2008 | A | CANC |
Troy Cobbley
|
|
|
Wrong inspection type called in.
|
INSP-Alarm Testing | 7/14/2008 | 7/15/2008 | 7/15/2008 | A | CANC |
Forrest France
|
|
|
Wrong inspection request type-"alarm testing" to be completed in conjunction with the project related FIR permit called in for afternoon inspection.
|
INSP-Alarm Testing | 7/11/2008 | 7/14/2008 | 7/14/2008 | P | CANC |
Troy Cobbley
|
|
|
The fire sprinklers where not quite ready when I was there to do the inspection. Will be rescheduled for tomorrow morning.
|
INSP-Sprinkler Rough-in/Hydro | 7/11/2008 | 7/14/2008 | 7/14/2008 | A | PASS |
Troy Cobbley
|
|
|
OH Hydro Inspection for the first floor passed
|
INSP-Sprinkler Rough-in/Hydro | 7/10/2008 | 7/11/2008 | 7/11/2008 | A | PASS |
Troy Cobbley
|
|
|
OH Hydro Inspection for the second floor passed.
|
INSP-Conference | 7/10/2008 | 7/10/2008 | 7/10/2008 | P | DONE |
Troy Cobbley
|
|
|
The conference was for the curved clouds in the first floor corridor. It appears that the way dave wants to install the sprinkler heads is acceptable and that floor coverage is being met.
|
INSP-Sprinkler Rough-in | 6/30/2008 | 7/1/2008 | 7/1/2008 | A | PART |
Forrest France
|
|
|
Forward flow of the DCVA backflow preventer completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 6/24/2008 | 6/26/2008 | 6/26/2008 | P | PART |
Forrest France
|
|
|
Hydrostatic testing for the FDC piping completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 6/24/2008 | 6/26/2008 | 6/26/2008 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler install is good for cover at the drop ceiling areas 1st floor and restrooms 2nd floor, reinspected noted defficiencies from the previous visit.
|
INSP-Sprinkler Rough-in | 6/19/2008 | 6/19/2008 | 6/19/2008 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping at the top of the east stair well can be covered. This was the extent of todays inspection. The plans were not marked.
|
INSP-Sprinkler Rough-in | 5/29/2008 | 5/30/2008 | 5/30/2008 | A | PART |
Troy Cobbley
|
|
|
This inspection was for a first floor rough-in. The sprinkler piping can not be covered yet since final locations for the pendants is not done. No t-bar has been installed yet. The rough-in for the most part is ok. Two items have been noted. They include most of the branchline hangers to the north of the 3" main have been attached to the bottom of the beams. I referenced note #50 which does not allow this. Also the sidewall head installed at the top of the elevator shaft has not been installed in the 4" to 6" window.
|
INSP-Sprinkler Rough-in | 5/27/2008 | 5/27/2008 | 5/27/2008 | P | FAIL |
Forrest France
|
|
|
Pendent head at the mechanical room 2nd floor is obstructed by an adjacent duct-need to relocate as discussed, remainder of hard lid ceilings are good for cover.
|
INSP-Sprinkler Rough-in/Hydro | 4/28/2008 | 4/28/2008 | 4/28/2008 | A | PART |
Forrest France
|
|
|
See locatons on approved plans set for rough-in areas inspected and okayed to date, noted shell protection sprig-ups at the common corridor 2nd floor are not installed-heads at this area may coincide with tenant permit work depending on job schedule.
|
INSP-Sprinkler Rough-in | 4/23/2008 | 4/25/2008 | 4/25/2008 | P | PART |
Forrest France
|
|
|
OH rough-in inspection completed for the second floor only at this time, see plans for areas not completed to date.
|
FIR-Aging Inspection | 2/13/2008 | 2/13/2008 | 2/13/2008 | | DEFR |
Forrest France
|
|
|
Site visit- building is under construction, work in progress.
|
Telephone call | | | 11/14/2007 | | DONE |
|
|
|
tlk to shawn ramsey ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 11/14/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/14/2007 | | 11/14/2007 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/14/2007 | | DONE |
|
|
|
|
Application received | | | 11/1/2007 | | |
|
|
|
|
Pending Assignment by SAM | 11/1/2007 | | | | |
|
|
|
|