INSP-Final Inspection | 6/4/2008 | 6/5/2008 | 6/5/2008 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 6/3/2008 | 6/4/2008 | 6/4/2008 | P | FAIL |
Troy Cobbley
|
|
|
The flow switch needs replaced and retested.
|
INSP-Sprinkler Rough-in/Hydro | 4/25/2008 | 4/28/2008 | 4/28/2008 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro for first and second floor complete. KR
|
INSP-Supply line flush | 4/22/2008 | 4/23/2008 | 4/23/2008 | P | PASS |
Troy Cobbley
|
|
|
The underground flush passed
|
INSP-Sprinkler Rough-in/Hydro | 4/22/2008 | 4/23/2008 | 4/23/2008 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro passed
|
INSP-Sprinkler Rough-in | 4/10/2008 | 4/10/2008 | 4/10/2008 | P | PASS |
Troy Cobbley
|
|
|
The underground sprinkler piping is ok to cover
|
INSP-Sprinkler Rough-in | 3/19/2008 | 3/20/2008 | 3/20/2008 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the two rooms where the sprinkler piping is ok to cover. I found one pendant head spaced too far from a wall in one of these two rooms. The fitter started correcting this prior to my leaving. The earthquake bracing. Also the last earthquake brace is missing from the below mezzanine piping. Prior to ceilings being installed below the mezzanine another rough-in inspection for armovers/hangers will be required. None of the overhead piping for the main fire sprinkler system was inspected. Per the fitter several heads are being added due to a large beam and a wall around the stairs. The added heads at the beam appear to end up in one of the remote areas. The plans will need to be resubmitted for verification of additional heads flowing water in the remote area. I notified the fitter of this.
|
INSP-Sprinkler Rough-in | 12/10/2007 | 12/11/2007 | 12/11/2007 | A | PART |
Troy Cobbley
|
|
|
The in building riser/stubout is ok to cover. The remaining underground has not been installed yet.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/29/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/29/2007 | | 11/29/2007 | | DONE |
|
|
|
|
Telephone call | | | 11/29/2007 | | DONE |
|
|
|
lft vm with sam ball ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 11/29/2007 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/29/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/2/2007 | | 11/28/2007 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Application received | | | 11/2/2007 | | |
|
|
|
|