INSP-Final Inspection | 5/2/2008 | 5/5/2008 | 5/5/2008 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Storage has been removed from the top of the couch storage bins.
|
INSP-Final Inspection | 5/1/2008 | 5/2/2008 | 5/2/2008 | A | FAIL |
Troy Cobbley
|
|
|
Need the pallets that have been placed on top of the couch storage boxes removed. I let the warehouse manager know that no items can be stored there. The PIV tamper switch needs adjusted so that it reports correctly. The forward flush passed. The trip tests of the two dry systems passed.
|
INSP-Final Inspection | 4/8/2008 | 4/11/2008 | 4/11/2008 | A | CANC |
Troy Cobbley
|
|
|
Per todd the inspection is to be canceled due to the fire alarm system not being ready.
|
INSP-Sprinkler Rough-in/Hydro | 4/2/2008 | 4/3/2008 | 4/3/2008 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test passed
|
INSP-Sprinkler Rough-in | 4/1/2008 | 4/2/2008 | 4/2/2008 | A | PASS |
Troy Cobbley
|
|
|
24hr Air Test started at 8:30 the left system has 45 psi and the right system has 44 psi.
|
Issue and Print Permit | | | 4/1/2008 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 3/28/2008 | 3/31/2008 | 3/31/2008 | A | PASS |
Troy Cobbley
|
|
|
OH Hydro Inspecion passed
|
Plan resubmittals received | | | 3/31/2008 | | |
|
|
|
|
Plan assigned to (SAM) | 3/31/2008 | | 3/31/2008 | | PASS |
Sam Rogers
|
|
|
3/31/2008 13:36:25 SLR - activity updated through activity FIRA22 from case FIR07-00929.
|
Sprinkler Plan Check | 3/31/2008 | | 3/31/2008 | | PASS |
Troy Cobbley
|
|
|
Modified plans reviewed by T. Coobley. New calc's acceptable. Plan annotations have been revised to stipulate the design commodities includes Plastics (couches) in wood crates less than 8' in height, not exceeding 1,000 sf; which is less than 10% of building, therefore classified as Miscellaneous Storage. Resubmitted hydraulic calculations based on the currently issued plans, verify the required EH2 density of 0.40gpm/sf/ over 1,000sf (the max. area of storage) is available without a fire pump. Therefore the currently issued sprinkler layout with no fire pump, based on Class IV piled commodities, with NO RACK STORAGE, is also acceptable for limited storage (not exceeding 1,000 sf) of Plastic commodity (couches in wooden crates) stored less than 8' in height. SLR
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/31/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/31/2008 | | 3/31/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 3/31/2008 | | DONE |
|
|
|
flt ms with receptionist for geradl ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 3/31/2008 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 3/26/2008 | 3/28/2008 | 3/28/2008 | A | PART |
Troy Cobbley
|
|
|
The overhead rough-in as far as piping installation is passed. The wrong heads have been installed. The correct sprinkler heads need to be installed or approval from the plan reviewer is required if they are to be left. The hose valves/piping as shown on the city approved plans has been removed as per Dave Hanniman.
|
INSP-Sprinkler Rough-in | 3/26/2008 | 3/27/2008 | 3/27/2008 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
Telephone call | | | 3/27/2008 | | DONE |
|
|
|
Telcon today with Randy Bowran, DeBest Fire Protection, ###-####, in follow up to our 3/23/08 telcon. Randy indicated the commodities include couches covered with a plastic bag, two-high, within in wooden 5-sided crates, (i.e. open on one side), with no plastic wrap or encapsulation around the wooden crate. I indicated that commodity falls under the "Plastic" commodity classification, per NFPA 13, TABLE A.5.6.4.1 ("Furniture-wood-with foam plastic cushioning"", not under the Class IV commodity class specified in their design criteria. Randy indicated the owner has agreed to remove all existing racks, and to store all couches in crates as described, along the north and east exterior walls, one crate high (7feet, each crate has an interior shelf so two couched are stored in each crate), and the total floor area occupied would be somewhat less than 1,000 sf. That arrangement would allow this Plastic storage to be considered as Miscellaneous storage, subject to NFPA 13, Chapter 13,;and Table 13.2.1 requires EH2 density of 0.40 gpm/sf/2500 sf. not considering the dry system adjustment. Randy agreed to recalculate the sprinkler system hydraulic performance over the specific floor area of the proposed couch storage to determine what density the system can provide. Randy will advise us of the calculation results and we will then decide whether the protection will be adequate as designed or if other protection measures will be required.
The permit shall not be "finaled" until this issue has been satisfactorily resolved.
|
INSP-Sprinkler Rough-in/Hydro | 3/25/2008 | 3/25/2008 | 3/26/2008 | P | PASS |
Troy Cobbley
|
|
|
UG Hydro Inspection passed for the underground supply and the remote fdc
|
Telephone call | | | 3/23/2008 | | DONE |
|
|
|
Per the fire alarm plans, there is no fire pump or pump room. I called Randy at DeBest (###-####) and learned that the design for the sprinkler FIR07-00929 permit is based on eliminating the fire pump (which was shown on FIR07-00374) at the request of the owner who told them he would eliminate rack storage and go to solid piled storage. I requested that we visit the site to verify that the owner intends to do that and if he has eliminated the racks yet. We do not want to approve the design/installation of a sprinkler design designed for solid piled storage unless they are willing to first eliminate the existing rack storage. He will set up an appointment for us to visit. Meantime, we are holding off on the approval of the fire alarm permit FIR08-00122.
|
INSP-Sprinkler Rough-in | 3/12/2008 | 3/13/2008 | 3/13/2008 | P | PASS |
Troy Cobbley
|
|
|
The remote FDC piping can be covered.
|
INSP-Sprinkler Rough-in | 3/11/2008 | 3/13/2008 | 3/12/2008 | A | CANC |
Troy Cobbley
|
|
|
UG Cover Inspection Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in | 3/10/2008 | 3/11/2008 | 3/11/2008 | P | PASS |
Troy Cobbley
|
|
|
Underground supply piping can be buried. Still need an inspection on the remote FDC piping. I suggested putting in the conduit for the PIV tamper as well prior to bury.
|
FIR-Aging Inspection | 3/5/2008 | 3/5/2008 | 3/7/2008 | | NR |
Troy Cobbley
|
|
|
WIP
|
Telephone call | | | 2/5/2008 | | DONE |
|
|
|
Per telcon with Gerald Eberly, this permit was intended to replace and supercede previously issued permit FIR07-00374. I requested he call the permit desk and request FIR07-00374 to be voided.
|
Inspection Record Card- Fire | 12/4/2007 | | 12/4/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/4/2007 | | |
|
|
|
|
Telephone call | | | 12/4/2007 | | DONE |
|
|
|
tlk to gerald ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 12/4/2007 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/4/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/13/2007 | | 11/30/2007 | | PASS |
|
|
|
Fire Sprinklers Permit Plan Review done by Bryan Johnson
|
Application received | | | 11/13/2007 | | |
|
|
|
|
Pending Assignment by SAM | 11/13/2007 | | | | |
|
|
|
|
Inspection Record Card- Fire | 3/31/2008 | | | | |
|
|
|
|