INSP-Final Inspection | 2/7/2008 | 2/8/2008 | 2/8/2008 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 12/18/2007 | 12/19/2007 | 12/19/2007 | A | PART |
Troy Cobbley
|
|
|
The large open retail area is ok to cover. Javier needs to relocate one pendant and add another due to sprinklers being over spaced.
|
Telephone call | | | 12/17/2007 | | DONE |
|
|
|
tlk to damaris ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 12/17/2007 | | |
|
|
|
|
Issue and Print Permit | | | 12/17/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/14/2007 | | |
|
|
|
|
Inspection Record Card- Fire | 12/14/2007 | | 12/14/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/5/2007 | | 12/13/2007 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Plan resubmittals received | | | 12/5/2007 | | DONE |
|
|
|
received 1 letter of transmittal, 1 fire sprinkler application, and 5 copies of sheet FP1 OF 1 sent to fire
|
Application received | | | 11/13/2007 | | |
|
|
|
|
Pending Assignment by SAM | 11/13/2007 | | | | |
|
|
|
|
Sprinkler Plan Check | 11/13/2007 | | | | FAIL |
|
|
|
These plans were denied due to lack of information and a design error.
Upon request, the denied set may be retrieved from my office for salvage. The denied set will be maintained for five working days.
|