INSP-Final Inspection | 2/26/2009 | 2/26/2009 | 2/26/2009 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 12/12/2008 | 12/12/2008 | 12/12/2008 | P | PART |
Forrest France
|
|
|
24 hr. air testing for the two dry systems passed.
|
INSP-Supply line flush | 7/8/2008 | 7/9/2008 | 7/9/2008 | A | PART |
Forrest France
|
|
|
UG fire supply line flush completed satisfactory.
|
INSP-Supply line flush | 7/8/2008 | 7/8/2008 | 7/8/2008 | P | PART |
Forrest France
|
|
|
Inspection request was intended for an underground hydrostatic test. Testing completed okay, hydro passed.
|
INSP-Sprinkler Rough-in | 11/19/2007 | 11/20/2007 | 11/20/2007 | A | FAIL |
Forrest France
|
|
|
UG fire supply line Install appears satisfactory, however no approved plans were left on site for verification of compliance with submitted plans.
|
Issue and Print Permit | | | 11/16/2007 | | DONE |
|
|
|
|
Application received | | | 11/14/2007 | | |
|
|
|
|
Sprinkler Plan Check | 11/14/2007 | | 11/14/2007 | | PASS |
|
|
|
Attached review comments to plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/14/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/14/2007 | | 11/14/2007 | | DONE |
|
|
|
|
Telephone call | | | 11/14/2007 | | DONE |
|
|
|
t/c w steve gaillard at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 11/14/2007 | | DONE |
|
|
|
|
Pending Assignment by SAM | 11/14/2007 | | | | |
|
|
|
|