INSP-Final Inspection | 7/14/2008 | 7/15/2008 | 7/15/2008 | A | PASS |
Forrest France
|
|
|
Chain and lock was added to PIV. New set of resubmitted plans were on site with all corrections made. KR
|
Telephone call | | | 7/14/2008 | | DONE |
Sam Rogers
|
|
|
Spoke with Bryan Johnson this morning. Plans have been approved and will be available for pick by applicant this afternooon.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/14/2008 | | DONE |
Cathy Brown
|
|
|
|
Inspection Record Card- Fire | 7/14/2008 | | 7/14/2008 | | DONE |
Cathy Brown
|
|
|
|
(F) Reprint permit | | | 7/14/2008 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/14/2008 | | DONE |
Barbara Stitt
|
|
|
|
Sprinkler Plan Check | 7/1/2008 | | 7/11/2008 | | PASS |
|
|
|
As-Built Plans & Calculations are approved By Bryan Johnson
|
Telephone call | | | 7/11/2008 | | DONE |
|
|
|
Herb, the GC, called inquiring about the progress of the fire sprinkler plan review. Informed Herb that the fire sprinkler plan reviewer has the fire sprinkler plans in his posession and the only case notes state that the "plans are on hold unitl further information recieved". Recommended he contact the sprinkler designer and/or permit applicant, American Fire Protection, to recieve further information regarding the delay of sprinkler plan approval.
|
Telephone call | | | 7/11/2008 | | DONE |
Sam Rogers
|
|
|
Received call from Jim Daines (American Fire Protection) regarding his concern about the length of time of the resubmitted fire sprinkler plan review. Informed Jim of the most recent case notes regarding "request for more information." Jim has been unsuccessful in his attempts to contact Johnson consulting for further information.
|
INSP-Final Inspection | 7/9/2008 | 7/10/2008 | 7/10/2008 | A | FAIL |
Forrest France
|
|
|
Plans are still under review for resubmittals.Fire sprinkler Inspection completed. One remaining item.Chain and lock is required on PIV. KR
|
Sprinkler Plan Check | 7/1/2008 | | 7/10/2008 | | NR |
|
|
|
These plans are on hold until further information is known.
Western Trailer FIR07-00935
Approved with Conditions 12/07/2007
Noted Conditions of Approval:
1. Provide an exterior control valve as required. An exterior indicating control valve is required for the fire sprinkler system in this building and provided with valve identification signage. (BMC 7-01-53 IFC 903.1.3) To be field verified. (Field verified by Inspector France but not reflected on the As-Builts)
2. The truck wash bay piping and material shall be corrosion resistant. Where corrosive conditions exist or piping is exposed to the weather, corrosion-resistant types of pipe, fittings, and hangers or protective corrosion-resistant coatings shall be used. (NFPA 13-7.7.5, 8.15.3.2.1*) To be field verified. (Not Verified or reflected on As-Builts)
3. Prior to final approval, an approved rack layout shall be verified to include 19’-0” maximum storage height in the parts warehouse in a single or double row rack configuration with 8’-0” aisles. (Rack Plans were submitted under a separate BLD permit and verified by inspector France. Racks were reflected on the As-Builts as an outline only)
(Recent plan review comments noted in red)
|
Override - Parcel Holds | | | 7/9/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 7/9/2008 | | |
|
|
|
|
Plan resubmittals received | | | 7/1/2008 | | |
Sam Rogers
|
|
|
|
Pending Assignment by SAM | 7/1/2008 | | 7/1/2008 | | DONE |
Sam Rogers
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 6/20/2008 | 6/20/2008 | 6/20/2008 | P | PART |
Forrest France
|
|
|
Verified some items per the C/N are finished including added heads at the wash bay, added seismic brace, spacing at the compressor room. Noted fire alarm work is nearly complete including tamper and flow switch wiring and FACP installation prior to the issuance of a fire alarm permit. Double permit fees will apply.
|
INSP-Sprinkler Rough-in/Hydro | 6/12/2008 | 6/12/2008 | 6/12/2008 | P | PART |
Forrest France
|
|
|
OH hydrostatic testing for both wet systems passed. OH rough-in failed due to overspaced heads at the wash bay, blocked heads at the compressor room, missing EQ brace at the 4" main NE corner of the warehouse, need to provide resubmittals for pipe size changes at the north office areas, some finish items at the riser are not complete including flex. couplings, FDC ball drip, head box, tagged DCVA, etc.
|
INSP-Sprinkler Rough-in | 5/30/2008 | 6/3/2008 | 6/3/2008 | P | PART |
Forrest France
|
|
|
1st and 2nd floor south offices OH rough-in is approved for cover with the exception of one missing EQ brace at the 2nd floor 3" main east side last piece.
|
Override - Parcel Holds | | | 5/30/2008 | | |
|
|
|
|
INSP-Sprinkler Rough-in | 4/11/2008 | 4/14/2008 | 4/14/2008 | A | PASS |
Troy Cobbley
|
|
|
The restroom, shower & locker room area are ok to cover. See the city approved plans for locations.
|
INSP-Sprinkler Rough-in/Hydro | 3/25/2008 | 3/25/2008 | 3/25/2008 | P | NR |
Forrest France
|
|
|
Not completed for inspection.
|
FIR-Aging Inspection | 3/20/2008 | 3/20/2008 | 3/20/2008 | | DEFR |
Forrest France
|
|
|
Work in progress, construction underway.
|
Issue permit | | | 12/14/2007 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/11/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/11/2007 | | 12/11/2007 | | DONE |
|
|
|
|
Telephone call | | | 12/11/2007 | | |
|
|
|
lft vm for jim danes ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 12/11/2007 | | DONE |
|
|
|
lft vm for jim danes ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 12/11/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/15/2007 | | 12/7/2007 | | PASS |
|
|
|
Plans are approved w/conditions by Bryan Johnson
|
Case Summary | | | 11/15/2007 | | DONE |
|
|
|
|
Application received | | | 11/15/2007 | | |
|
|
|
|
Pending Assignment by SAM | 11/15/2007 | | | | |
|
|
|
|