INSP-Final Inspection | 3/18/2008 | 3/19/2008 | 3/19/2008 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 3/17/2008 | 3/18/2008 | 3/18/2008 | A | FAIL |
Forrest France
|
|
|
Provide service tag at the riser, provide "911" sign at the outside bell, missing escutcheons at some locations, one blocked head at a kitchen area by an adjacent light fixture.
|
INSP-Sprinkler Rough-in/Hydro | 3/17/2008 | 3/17/2008 | 3/17/2008 | P | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test completed satisfactory.
|
INSP-Supply line flush | 3/17/2008 | 3/17/2008 | 3/17/2008 | P | PART |
Forrest France
|
|
|
UG fire supply line flush completed in conjunction with United Water company.
|
CHANGE STATUS TO (ISS) | | | 3/17/2008 | | |
|
|
|
already issued previously-- gave plans to customer
|
Inspection Record Card- Fire | 3/14/2008 | | 3/14/2008 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 3/14/2008 | | DONE |
|
|
|
t/c w brook nelson at ###-#### - permit ready and no fee
|
Permit Ready to Issue | | | 3/14/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/14/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/4/2008 | | 3/12/2008 | | PASS |
|
|
|
as-built plans and calculations approved
|
Plan resubmittals received | | | 3/4/2008 | | |
|
|
|
Plan modification: received three copies of application, hydraulic calculations, product info, and four copies of sheets FP-1, FP-2; routed to fire review
|
INSP-Sprinkler Rough-in | 2/20/2008 | 2/21/2008 | 2/21/2008 | A | CANC |
Forrest France
|
|
|
Per bruce.
|
INSP-Sprinkler Rough-in/Hydro | 12/24/2007 | 12/26/2007 | 12/26/2007 | A | PART |
Forrest France
|
|
|
Verified tenting installation at the third floor. OH fire sprinkler piping is okay for cover pending satisfactory plan resubmittals reflecting field modifications in piping layout including main/branch lines and changed head locations.
|
INSP-Sprinkler Rough-in | 12/24/2007 | 12/24/2007 | 12/24/2007 | P | PART |
Forrest France
|
|
|
OH hydrostatic retest completed and passed per inspection done 12/21. No access provided to perform inspection for cover at the third floor today, noted insulation at the third floor does not appear to be finished at this time.
|
INSP-Sprinkler Rough-in/Hydro | 12/18/2007 | 12/19/2007 | 12/19/2007 | A | FAIL |
Forrest France
|
|
|
OH Hydrostatic test failed due to 25 psi. pressure loss at the guage.
|
INSP-Sprinkler Rough-in | 12/17/2007 | 12/17/2007 | 12/18/2007 | P | NR |
Forrest France
|
|
|
bruce - please call 1/2 hr prior to inspection Phone #: ###-####
|
INSP-Sprinkler Rough-in | 12/13/2007 | 12/14/2007 | 12/14/2007 | A | FAIL |
Forrest France
|
|
|
Noted significant changes regarding the actual installation v. approved plans (main and branchline changes, supply riser changes, added heads, relocated sw heads, etc.), noted missing heads at closets on the 2nd floor, missing heads under the stairs 1st floor, added heads in mech, closets, branchline changes at the design area, noted the UG supply has been installed and covered without an inspection and will not be accepted until conditions of approval are met.
|
INSP-Sprinkler Rough-in | 12/13/2007 | 12/13/2007 | 12/13/2007 | P | CANC |
Forrest France
|
|
|
Inspection to be rescheduled as discussed, noted contractor has been issued the permit and called for a system rough-in inspection the same day.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/13/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/13/2007 | | 12/13/2007 | | DONE |
|
|
|
|
Telephone call | | | 12/13/2007 | | DONE |
|
|
|
lft ms with receptionist for brooks ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 12/13/2007 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/13/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/19/2007 | | 12/10/2007 | | PASS |
|
|
|
These plans were approved per attached comments with conditions by Bryan Johnson
|
Application received | | | 11/19/2007 | | |
|
|
|
|
Pending Assignment by SAM | 11/19/2007 | | | | |
|
|
|
|