Miscellaneous action | | | 12/16/2011 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 6/15/2010 | 6/15/2010 | 6/15/2010 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 6/7/2010 | 6/8/2010 | 6/8/2010 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping is ok to cover.
|
INSP-Conference | 5/5/2010 | 5/6/2010 | 5/6/2010 | A | DONE |
Troy Cobbley
|
|
|
I spoke to Mike about not requiring a new permit and that this permit can be finished as long as the new work matched what was originally submitted.
|
Miscellaneous action | | | 3/11/2010 | | DONE |
|
|
|
Sent email requesting project status.
|
Telephone call | | | 3/8/2010 | | DONE |
|
|
|
Talked with Lisa at Absolute. Lisa said she would look into the status of the project and get back to me.
|
FIR-Aging Inspection | 4/25/2008 | 4/25/2008 | 4/28/2008 | | NR |
Troy Cobbley
|
|
|
Job not ready as per Mike Oswald. KR
|
CHANGE STATUS TO (ISS) | | | 1/30/2008 | | DONE |
|
|
|
alreadly issued previously
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/28/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/28/2008 | | 1/28/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 1/28/2008 | | DONE |
|
|
|
tlk to lisa at absolute fire protection ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 1/28/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/16/2008 | | 1/22/2008 | | PASS |
|
|
|
This review was the result of a plan modification. 15 heads were affected as a result of the modification - *As -Built plans approved as submitted by Bryan Johnson
|
Plan resubmittals received | | | 1/17/2008 | | |
|
|
|
received "5" sets of plans & application with each set -- plans put on fire shelf
|
Issue and Print Permit | | | 1/7/2008 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/31/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/31/2007 | | 12/31/2007 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 12/31/2007 | | DONE |
|
|
|
lft vm with greg johnson ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 12/31/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/13/2007 | | 12/28/2007 | | PASS |
|
|
|
Plans are approved as submitted by Bryan Johnson
|
Case Summary | | | 12/13/2007 | | DONE |
|
|
|
|
Application received | | | 12/13/2007 | | |
|
|
|
|
Pending Assignment by SAM | 12/13/2007 | | | | |
|
|
|
|