INSP-Final Inspection | 10/7/2008 | 10/8/2008 | 10/8/2008 | A | PASS |
Forrest France
|
|
|
Items on C/N finished, forward flow testing passed, outside bell adjusted while on site, overhead fire sprinkler permit finaled.
|
INSP-Final Inspection | 10/2/2008 | 10/6/2008 | 10/6/2008 | A | CANC |
Troy Cobbley
|
|
|
Mike Bierman is the contact. Thanks. Phone #: ###-#### Internet Inspection Request from: Stan Beus
|
INSP-Sprinkler Rough-in | 7/11/2008 | 7/14/2008 | 7/14/2008 | A | PART |
Troy Cobbley
|
|
|
The earthquake bracing as noted in the previous inspection has not been corrected and the upright heads on the second floor that were spaced too close together have not been corrected either. Leroy and I agreed they could be verified at the final inspection.
|
INSP-Sprinkler Rough-in/Hydro | 7/1/2008 | 7/2/2008 | 7/2/2008 | P | FAIL |
Forrest France
|
|
|
OH rough-in inspection failed due to several items including 1st floor overspaced corner, elevator pit SW too high, noted added heads at entry vestibule, relocate EQ brace at office 103 if intended for the adjacent main longitudinal-see detail on plan set, warehouse area is missing proper temp. heads at the unit heater zones (13), noted two added heads and two deleted heads not required due to construction changes, one overspaced corner at the warehouse, 2nd floor office area missing two ssu heads, mixed temp. at one area, 4 heads exceed min. spacing, an additonal corner is overspaced. See locations marked in red on approved plan set for defficiencies. NOTE: Overhead hydrostatic test for both wet systems passed.
|
FIR-Aging Inspection | 5/6/2008 | 5/6/2008 | 5/6/2008 | | DEFR |
Forrest France
|
|
|
Need site inspection request
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/5/2008 | | DONE |
|
|
|
|
Telephone call | | | 2/5/2008 | | DONE |
|
|
|
lft vm for lilly scales ###-#### that permit and fees are ready to be picked up
|
Inspection Record Card- Fire | 2/5/2008 | | 2/5/2008 | | DONE |
Cathy Brown
|
|
|
|
Issue and Print Permit | | | 2/5/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/23/2008 | | 2/4/2008 | | PASS |
|
|
|
Plan are approved by Bryan Johnson
|
Plan resubmittals received | | | 1/23/2008 | | |
|
|
|
Received application, five binders and pages FP1, FP2, FP3; taken to fire review
|
Sprinkler Plan Check | 12/18/2007 | | 1/4/2008 | | FAIL |
|
|
|
The plans were rejected due to missing or lack of information. Upon request, the denied set may be retrieved from my office for salvage. The denied set will be maintained for five working days.
|
Case Summary | | | 12/18/2007 | | DONE |
|
|
|
|
Application received | | | 12/18/2007 | | |
|
|
|
|
Pending Assignment by SAM | 12/18/2007 | | | | |
|
|
|
|