INSP-Final Inspection | 1/15/2008 | 1/16/2008 | 1/16/2008 | A | PASS |
Forrest France
|
|
|
Fire sprinkler work passed final inspection, two pendents adjusted while on site, field modifications acceptable, permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 1/10/2008 | 1/11/2008 | 1/11/2008 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover
|
Issue and Print Permit | | | 1/2/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/21/2007 | | 12/21/2007 | | PASS |
Scott Arellano
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/21/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/21/2007 | | 12/21/2007 | | DONE |
|
|
|
|
Telephone call | | | 12/21/2007 | | DONE |
|
|
|
tlk to jim danes ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 12/21/2007 | | DONE |
|
|
|
|
Case Summary | | | 12/19/2007 | | DONE |
|
|
|
|
Application received | | | 12/19/2007 | | |
|
|
|
|
Pending Assignment by SAM | 12/19/2007 | | | | |
|
|
|
|