Permit Information
Permit NumberFIR07-01031
StatusFinaled
Name SIMPLEX/GRINNELL
Site Address 1130 N ALLUMBAUGH ST
Project NameValley View Independant Living
Customer Number 
ePlanReview 
Description
Original Scope of Work:
The scope if work includes modifying the existing wet and dry systems to meet requirements through out the heated and cold attic spaces. The existing wet system will be modified by adding and relocating new quick response heads in the existing corridors and remodeled areas and adding a new system in the new construction area’s. The attic dry system will be modified to protect a new area. The modification includes extending the existing dry pipe main out into the new attic space. The new attic space will be protected with BB1 attic heads. The existing riser shall be modified to include a listed double check back flow device.
The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD07-01834.
Valley View Retirement Center: Independent Living Facility FIR07-01031
06/12/08 Revised Scope of work:
Replace standard response heads in the corridors and remodeled areas only to a quick response type.
Add a forward flow device to the existing fire sprinkler riser room.
Add a new backflow device to the existing fire sprinkler system.
Add to the existing fire sprinkler system to accommodate the new additions.
Replace existing air compressor with new general air. Model # LT20033*.
06/12/08 Comments:
The existing air compressor shall meet the dry system 30 minute recovery time as required, or be replace with a new compressor the would meet the recovery time. To be field verified.
Add a forward flow assembly at the riser. (NFPA 10.10.2.5) To be field verified.
Independent living 07-01031 change out existing standard to quick response heads in the existing corridors, new construction and remolded areas only. Existing standard response shall remain in all other areas. See Attached Campbell & Associates, Inc. letter dated 05/20/08.
All heads affected with in the scope of work shall meet current code requirements for obstructions in accordance with NFPA 13 8.6.5. To be field verified.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/7/200910/7/200910/7/2009PPASS
DetailsTroy Cobbley
permit finaled
INSP-Sprinkler Rough-in9/24/20099/25/20099/25/2009APASS
DetailsTroy Cobbley
See the city approved plans for piping locations ok to cover.
INSP-Sprinkler Rough-in/Hydro9/17/20099/21/20099/21/2009PPASS
DetailsTroy Cobbley
Overhead hydo test passed.
INSP-Sprinkler Rough-in/Hydro9/14/20099/17/20099/17/2009PCANC
DetailsForrest France
James Phone #: ###-####
INSP-Sprinkler Rough-in8/27/20098/28/20098/28/2009APASS
DetailsTroy Cobbley
See the city approved plans for location with todays date where sprinkler piping is ok to cover.
INSP-Sprinkler Rough-in8/5/20098/6/20098/6/2009APASS
DetailsTroy Cobbley
See the city approved plans for locations near the main entrance where the sprinkler piping is ok to cover.
INSP-Final Inspection7/1/20097/1/20097/1/2009PPART
DetailsTroy Cobbley
Sprinklers are complete in Beauty, Mail Room, Activities, Massage and Office.
INSP-Sprinkler Rough-in6/23/20096/24/20096/24/2009APASS
DetailsTroy Cobbley
See the city approved plans for rooms where the sprinkler piping can be covered
INSP-Final Inspection6/19/20096/22/20096/22/2009APART
DetailsTroy Cobbley
The dining area and interior connecting corridor sprinklers are complete.
INSP-Sprinkler Rough-in6/16/20096/17/20096/17/2009PPART
DetailsTroy Cobbley
See the city approved plans for locations where the sprinkler piping is ok for cover dated for today.
Override - Parcel Holds6/16/20091/1/19006/16/2009  
not in affected area
INSP-Sprinkler Rough-in6/10/20096/11/20096/11/2009APASS
DetailsTroy Cobbley
The entry, side offices and activities room are ok for final. The dining area sprinkler piping has been covered prior to a rough-in inspection. The piping shall be exposed for inspection.
Override - Parcel Holds  6/10/2009  
INSP-Sprinkler Rough-in5/26/20095/26/20095/27/2009PPASS
DetailsTroy Cobbley
See the on site as-builts for locations with todays date where the sprinkler piping can be covered.
CHANGE STATUS TO (ISS)  5/21/2009 DONE
(F) Reprint permit  5/21/2009  
Plan assigned to (Tim)5/18/2009 5/20/2009 DONE
DetailsTim Frost
5/20/2009 13:32:00 TRF - activity updated through activity FIRA22 from case FIR07-01031.
Sprinkler Plan Check5/20/2009 5/20/2009 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.

Plan Modifications 05-20-09
Ballooned sections of the plans were reviewed due to plan modification. Several areas were marked in red on the plans. The marked areas require verification that the areas are non-combustible as defined in NFPA 13: 8.15.1.1 Concealed Spaces Requiring Sprinkler Protection. All concealed spaces enclosed wholly or partly by exposed combustible construction shall be protected by sprinklers except in concealed spaces where sprinklers are not required to be installed by 8.15.1.2.1 through 8.15.1.2.16 and 8.15.6. If the areas are not non combustible as defined above then additional sprinklers are required.

In addition, one sprinkler was over spaced.

Field Inspector, please verify compliance with the above items
PLANS/APPL TAKEN TO FRONT DESK  5/20/2009 DONE
DetailsTim Frost
Telephone call  5/20/2009 DONE
Details
left vm for brad at ###-#### - permit (plan mod) ready and no fees due
Permit Ready to Issue  5/20/2009 DONE
Details
Pending Assignment by SAM12/20/2007 5/18/2009 DONE
DetailsTisha Gallop
5/18/2009 15:32:54 LEG - activity updated through activity FIRA158 from case FIR07-01031.
Case Summary  5/18/2009 DONE
Plan resubmittals received  5/18/2009  
DetailsTisha Gallop
Plan Modification: Received application and three copies of submittal documents and plan sheets FP1, FP2, FP3, FP4, FP5, FP6, FP7; taken to fire review
INSP-Sprinkler Rough-in5/13/20095/13/20095/13/2009PPASS
DetailsTroy Cobbley
See the city approved plans for locations with todays date where the sprinkler piping can be covered.
INSP-Conference5/8/20095/11/20095/11/2009APASS
DetailsTroy Cobbley
The as-built plans have been consolidated to a single set of plans for each area. As per Brad copies of these two plans will be submitted to the city of boise for their final review. These set of plans to be used for all future inspections.
INSP-Sprinkler Rough-in4/20/20094/21/20094/21/2009APASS
DetailsTroy Cobbley
The sprinkler piping above the existing sheet rock ceiling is ok to cover. The sprinkler piping as installed does not match the city approved plans and will need to be resubmitted with all of the other changes for approval prior to final.
INSP-Final Inspection2/17/20092/18/20092/18/2009PPART
DetailsTroy Cobbley
The north and south ends of the ILF are finished
INSP-Sprinkler Rough-in2/12/20092/13/20092/13/2009APASS
DetailsTroy Cobbley
See the city approved plans for locations where the sprinkler piping can be covered. Sprinkler work is complete in the first and second floor skilled nursing dining areas and in the central core (main building) first and second floors.
INSP-Sprinkler Rough-in2/9/20092/10/20092/10/2009APASS
DetailsTroy Cobbley
See the approved plans for corridor piping that can be covered.
INSP-Sprinkler Rough-in1/20/20091/21/20091/22/2009PPASS
DetailsTroy Cobbley
See the as-builts with the date of 1-21-2009 for the location where the sprinkler piping is ok to cover
INSP-Sprinkler Rough-in12/17/200812/18/200812/18/2008PPASS
DetailsTroy Cobbley
See the as-built plans for locations in the main lobby where sprinkler piping is ok to cover.
INSP-Sprinkler Rough-in12/4/200812/4/200812/4/2008PPASS
DetailsTroy Cobbley
See the as-built plans for the second floor room that is ok to cover the piping.
INSP-Sprinkler Rough-in12/3/200812/3/200812/3/2008PFAIL
DetailsForrest France
Inspection for cover at the 1st floor lobby 09 and the 2nd floor conference room 327 failed due to field modificaitons beyond the limits of in field approvals via as-built plans- noted pipe size, branchline and head number inconsistencies.
INSP-Sprinkler Rough-in11/12/200811/13/200811/13/2008APART
DetailsTroy Cobbley
See the city approved plans for locations where sprinkler piping can be covered. I noted flat face bushing being used on the second floor and showed the fitter the code section that prohibits their use. Also the second floor piping as installed does not match the approved drawings.
INSP-Sprinkler Rough-in7/14/20087/15/20087/15/2008APASS
DetailsTroy Cobbley
The piping tie-ins for the overbuilds has been completed. In many locations the existing cpvc piping is exposed in the attic space due to the insulation settling or being knocked down. This led to a freeze up last winter. I notified the general contractor of the importance of getting this repaired and could hold up occupancy for the new areas. He stated that the owners were aware of the problem and are getting bids from contractors to get the problem fixed.
INSP-Sprinkler Rough-in7/1/20087/2/20087/2/2008APART
DetailsForrest France
See redlined areas on city approved plans for areas ok to cover. KR
INSP-Sprinkler Rough-in6/27/20086/27/20086/27/2008PPART
DetailsForrest France
See red line areas on plans for areas ok to cover.KR
PLANS/APPL TAKEN TO FRONT DESK  6/13/2008 DONE
DetailsCathy Brown
Override - Parcel Holds  6/13/2008  
Override - Parcel Holds  6/13/2008  
Override - Parcel Holds  6/13/2008  
Inspection Record Card- Fire6/13/2008 6/13/2008 DONE
DetailsCathy Brown
Telephone call  6/13/2008 DONE
Details
t/c w tyson smith at ###-#### - permit ready and fees given
Override - Parcel Holds  6/13/2008  
Override - Parcel Holds  6/13/2008  
Override - Parcel Holds  6/13/2008  
Permit Ready to Issue  6/13/2008 DONE
Details
Override - Parcel Holds  6/13/2008  
Override - Parcel Holds  6/13/2008  
Override - Parcel Holds  6/13/2008  
Issue and Print Permit  6/13/2008 DONE
Sprinkler Plan Check5/21/2008 6/11/2008 PASS
Details
Plans are approved with Conditions by Bryan Johnson
(F) Reprint permit  5/21/2008 DONE
Plan resubmittals received  5/21/2008  
Received letter and four copies of application, United Water Flow sheet, hydraulic calculations, product data, and sheets FP1, FP2, FP3, FP4, FP5, FP6; taken to fire review
Case Summary  12/20/2007 DONE
Application received  12/20/2007