INSP-Final Inspection | 10/9/2009 | 10/9/2009 | 10/9/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 10/6/2009 | 10/6/2009 | 10/6/2009 | P | CANC |
Troy Cobbley
|
|
|
Wrong permit number called in for inspection.
|
INSP-Sprinkler Rough-in | 9/17/2009 | 9/21/2009 | 9/21/2009 | P | CANC |
Troy Cobbley
|
|
|
Duplicate inspection
|
INSP-Sprinkler Rough-in/Hydro | 9/17/2009 | 9/21/2009 | 9/21/2009 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 9/14/2009 | 9/17/2009 | 9/17/2009 | P | CANC |
Forrest France
|
|
|
James Phone #: ###-####
|
INSP-Sprinkler Rough-in | 9/9/2009 | 9/10/2009 | 9/10/2009 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where the piping can be covered.
|
INSP-Sprinkler Rough-in | 9/4/2009 | 9/8/2009 | 9/8/2009 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the piping that is ok for cover.
|
INSP-Sprinkler Rough-in | 9/2/2009 | 9/3/2009 | 9/3/2009 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler piping in the residence rooms as marked on the city approved plans is ok to cover.
|
INSP-Sprinkler Rough-in | 8/18/2009 | 8/18/2009 | 8/19/2009 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping in the kitchen area can be covered.
|
INSP-Sprinkler Rough-in | 8/13/2009 | 8/14/2009 | 8/14/2009 | A | FAIL |
Troy Cobbley
|
|
|
James Phone #: ###-#### The contact did not answer the phone and I did not know which areas were to be inspected. I did re-inspect in the kitchen but found combustibles still present above the ceiling.
|
INSP-Sprinkler Rough-in | 8/11/2009 | 8/12/2009 | 8/12/2009 | A | PART |
Troy Cobbley
|
|
|
See the city approved plans for the piping/rooms in the kitchen area that passed rough-in. The piping can not be covered due to combustibles located above the ceiling that need addressed. I spoke to John with Petra about this item.
|
INSP-Sprinkler Rough-in | 8/7/2009 | 8/10/2009 | 8/10/2009 | P | CANC |
Troy Cobbley
|
|
|
James-cover up inspection please Phone #: ###-#### Cancelled per Jim.
|
INSP-Final Inspection | 6/30/2009 | 6/30/2009 | 6/30/2009 | P | PART |
Troy Cobbley
|
|
|
The sprinklers are complete in the new shower room of skilled nursing second floor.
|
INSP-Final Inspection | 6/29/2009 | 6/29/2009 | 6/29/2009 | P | PART |
Troy Cobbley
|
|
|
1st & 2nd Floor area B of Skilled Nursing Sprinklers Complete
|
INSP-Sprinkler Rough-in/Hydro | 6/23/2009 | 6/24/2009 | 6/24/2009 | A | PASS |
Troy Cobbley
|
|
|
The hydro test for the new piping in skilled nursing, first floor, passed.
|
INSP-Sprinkler Rough-in | 6/19/2009 | 6/22/2009 | 6/22/2009 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations with todays date where the sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in | 6/18/2009 | 6/19/2009 | 6/19/2009 | P | DEFR |
Forrest France
|
|
|
jim Phone #: ###-####
|
INSP-Sprinkler Rough-in | 6/16/2009 | 6/17/2009 | 6/17/2009 | P | PART |
Troy Cobbley
|
|
|
See the on site as-built plans for locations where the sprinkler piping is ok for cover dated for today.
|
Override - Parcel Holds | 6/16/2009 | 1/1/1900 | 6/16/2009 | | |
|
|
|
Not in affected area
|
CHANGE STATUS TO (ISS) | | | 6/5/2009 | | DONE |
|
|
|
finaled by mistake - changed back to issue per troy cobbley
|
INSP-Final Inspection | 6/2/2009 | 6/3/2009 | 6/3/2009 | A | PASS |
Troy Cobbley
|
|
|
The sprinklers are complete in the new first floor exit passage way at the skilled nursing area.
|
Override - Parcel Holds | 6/2/2009 | 1/1/1900 | 6/2/2009 | | |
|
|
|
final sprinkler
|
CHANGE STATUS TO (ISS) | | | 5/21/2009 | | DONE |
|
|
|
|
(F) Reprint permit | | | 5/21/2009 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/20/2009 | | 5/20/2009 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
Plan Modifications 05-20-09
Ballooned sections of the plans were reviewed due to plan modification. Several areas were marked in red on the plans. The marked areas require verification that the areas are non-combustible as defined in NFPA 13: 8.15.1.1 Concealed Spaces Requiring Sprinkler Protection. All concealed spaces enclosed wholly or partly by exposed combustible construction shall be protected by sprinklers except in concealed spaces where sprinklers are not required to be installed by 8.15.1.2.1 through 8.15.1.2.16 and 8.15.6. If the areas are not non combustible as defined above then additional sprinklers are required.
In addition, one sprinkler was to close to another and could cause a cold soldering problem.
Field Inspector, please verify compliance with the above items.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/20/2009 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 5/20/2009 | | DONE |
|
|
|
left vm for brad at ###-#### - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 5/20/2009 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 5/18/2009 | | 5/20/2009 | | DONE |
Tim Frost
|
|
|
5/20/2009 10:57:57 TRF - activity updated through activity FIRA22 from case FIR07-01032.
|
Meeting | | | 5/18/2009 | | DONE |
Tim Frost
|
|
|
Intake meeting with Brad from Simplex/Grinnell. We reviewed the plan modifications. Most of the changes were minor. (Shifting sprinklers in the corridors due to a new ceiling layout.)
|
Case Summary | | | 5/18/2009 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/18/2009 | | |
Tisha Gallop
|
|
|
Plan Modification: Received application, three copies of submittal documents and plan sheets FP1, FP2, FP3; taken to fire review.
|
Pending Assignment by SAM | 12/20/2007 | | 5/18/2009 | | DONE |
Tisha Gallop
|
|
|
5/18/2009 14:46:34 LEG - activity updated through activity FIRA158 from case FIR07-01032.
|
INSP-Sprinkler Rough-in | 5/13/2009 | 5/13/2009 | 5/13/2009 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations with todays date where the sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 5/11/2009 | 5/12/2009 | 5/12/2009 | A | PASS |
Troy Cobbley
|
|
|
See the new ste of as-builts for location with todays date where the sprinkler piping is ok to cover. This includes the skilled nursing, second floor are a"B". Also the hydro test for this area passed.
|
INSP-Sprinkler Rough-in | 5/11/2009 | 5/11/2009 | 5/11/2009 | P | CANC |
Troy Cobbley
|
|
|
Will need to be rescheduled due to time constraints.
|
INSP-Sprinkler Rough-in/Hydro | 5/11/2009 | 5/11/2009 | 5/11/2009 | P | FAIL |
Troy Cobbley
|
|
|
The above ground hydro test for the second floor of the skilled nursing failed.
|
INSP-Sprinkler Rough-in/Hydro | 5/8/2009 | 5/11/2009 | 5/11/2009 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations with todays date where the sprinkler piping can be covered.
|
INSP-Conference | 5/8/2009 | 5/11/2009 | 5/11/2009 | A | PASS |
Troy Cobbley
|
|
|
The as-built plans have been consolidated to one set of plans for each of the two areas. As per Brad copies of these two plans will be submitted to the city of boise for their final review. These set of plans to be used for all future inspections.
|
INSP-Sprinkler Rough-in | 5/4/2009 | 5/5/2009 | 5/5/2009 | A | FAIL |
Troy Cobbley
|
|
|
No inspection was performed due to the city approved plans and as-builts not matching the installation. Provide city approved plans that match the installation.
|
INSP-Sprinkler Rough-in | 4/30/2009 | 5/1/2009 | 5/1/2009 | A | PASS |
Troy Cobbley
|
|
|
This was for a conference in the shower areas dealing with pendant sprinkler coverage and curtains.
|
INSP-Sprinkler Rough-in | 4/29/2009 | 4/29/2009 | 4/29/2009 | P | PASS |
Troy Cobbley
|
|
|
I went over sprinkler coverage under soffits in the second floor of the skilled nursing area. It appears that the placement of the pendant sprinkler heads will provide adequate coverage.
|
INSP-Final Inspection | 2/23/2009 | 2/24/2009 | 2/24/2009 | P | PART |
Troy Cobbley
|
|
|
The sprinkler work is complete in both the first floor and second floor dining areas. An ok to cover was also given for the first floors nurses station. See the city approved plans for the exact area covered with todays date and my signature.
|
INSP-Final Inspection | 2/17/2009 | 2/18/2009 | 2/18/2009 | A | PART |
Troy Cobbley
|
|
|
The north and south ends of the ILF are finished.
|
INSP-Sprinkler Rough-in/Hydro | 2/5/2009 | 2/5/2009 | 2/5/2009 | P | PASS |
Troy Cobbley
|
|
|
The hydro test for the first floor skilled nursing dining room passed.
|
INSP-Sprinkler Rough-in/Hydro | 1/29/2009 | 1/30/2009 | 1/30/2009 | A | PASS |
Troy Cobbley
|
|
|
The hydro test for the second floor skilled nurse dining area passed.
|
INSP-Sprinkler Rough-in | 1/28/2009 | 1/29/2009 | 1/29/2009 | A | PASS |
Troy Cobbley
|
|
|
See the dated as-built plans for the second floor skilled nursing area where sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in | 1/22/2009 | 1/22/2009 | 1/23/2009 | P | FAIL |
Troy Cobbley
|
|
|
The hydro test for the second floor skilled nursing dining area failed.
|
INSP-Sprinkler Rough-in | 1/20/2009 | 1/21/2009 | 1/22/2009 | A | PASS |
Troy Cobbley
|
|
|
See the as-builts with the date of 1-21-2009 for the location where the sprinkler piping is ok to cover
|
INSP-Sprinkler Rough-in | 1/6/2009 | 1/7/2009 | 1/7/2009 | P | PASS |
Troy Cobbley
|
|
|
See the second floor as-built plans for the corridor and dining areas that are approved for cover.
|
INSP-Sprinkler Rough-in | 11/14/2008 | 11/17/2008 | 11/17/2008 | A | PART |
Forrest France
|
|
|
Overhead install at the new exterior porch adjacent to the skilled nursing area 1st floor okayed for cover, also verified as-builts for field modifications at the 2nd floor dining area.
|
FIR-Aging Inspection | 9/12/2008 | 9/12/2008 | 9/12/2008 | | NR |
Troy Cobbley
|
|
|
Work is in progress
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Inspection Record Card- Fire | 6/13/2008 | | 6/13/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/13/2008 | | DONE |
|
|
|
|
Telephone call | | | 6/13/2008 | | DONE |
|
|
|
t/c w tyson smith at ###-#### - permit ready and fees given
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Permit Ready to Issue | | | 6/13/2008 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 6/13/2008 | | |
|
|
|
|
Issue and Print Permit | | | 6/13/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/21/2008 | | 6/12/2008 | | PASS |
|
|
|
plans are approved
|
(F) Reprint permit | | | 5/21/2008 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/21/2008 | | |
|
|
|
Received letter and four copies of application, United Water Flow sheet, hydraulic calculations, product data, and sheets FP1, FP2, FP3; taken to fire review
|
Sprinkler Plan Check | 4/17/2008 | | 4/30/2008 | | FAIL |
|
|
|
These plans were denied because the scope of work did not meet the construction specifications set by the PE. Upon request the denied set of plans may be retrieved from my office for salvage.
|
(F) Reprint permit | | | 4/17/2008 | | |
|
|
|
|
Plan resubmittals received | | | 4/17/2008 | | |
|
|
|
received "4" sets of applications, & "4" sets of plans including each sheet of FP1, FP2, & FP3-- plans put on fire shelf
|
Sprinkler Plan Check | 12/20/2007 | | 1/8/2008 | | FAIL |
|
|
|
These plans were denied due to missing required equipment and lack of information. Upon request, the denied set of plans may be retrieved from my office for salvage.
|
Application received | | | 12/20/2007 | | |
|
|
|
|
Case Summary | | | 12/20/2007 | | DONE |
|
|
|
|