INSP-Final Inspection | 2/23/2009 | 2/23/2009 | 2/23/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Telephone call | | | 2/23/2009 | | DONE |
Tim Frost
|
|
|
Spoke to the electrican Bill Payne @ Bosie Basin Electric. He confirmed that the electrical heat tracing of the fire protection main was installed exactly per the listing information. Forest France confirmed that he inspected the monitoring of the heat tracing and it worked properly. The heat tracing appears to conform with all requirments of NFPA 13, 2007, 8.16.4
See attached heat tracing listing.
|
INSP-Final Inspection | 2/18/2009 | 2/19/2009 | 2/19/2009 | A | PART |
Forrest France
|
|
|
See inspection comments per T. Frost.
|
INSP-Final Inspection | 2/17/2009 | 2/18/2009 | 2/18/2009 | A | PART |
Forrest France
|
|
|
Sprinkler system interconnections to the fire alarm panel for trouble, supervisory, and alarm conditions completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 12/29/2008 | 12/29/2008 | 12/29/2008 | P | PART |
Forrest France
|
|
|
1st floor install okay for cover only as noted on approved plans.
|
INSP-Sprinkler Rough-in/Hydro | 12/12/2008 | 12/12/2008 | 12/12/2008 | A | PART |
Forrest France
|
|
|
Pneumatic dry systems test complete.
|
INSP-Sprinkler Rough-in/Hydro | 12/10/2008 | 12/11/2008 | 12/11/2008 | P | PART |
Forrest France
|
|
|
24 hr. air testing completed and passed for both dry systems.
|
INSP-Sprinkler Rough-in/Hydro | 12/10/2008 | 12/10/2008 | 12/10/2008 | A | PART |
Forrest France
|
|
|
Begin 24 hr. pneumatic testing for both dry systems each at 41psig @12:40.
|
INSP-Sprinkler Rough-in/Hydro | 12/1/2008 | 12/1/2008 | 12/1/2008 | A | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 11/28/2008 | 11/28/2008 | 11/28/2008 | P | PART |
Forrest France
|
|
|
Okay to cover 1st floor rough-in per plan annotations.
|
INSP-Sprinkler Rough-in/Hydro | 11/24/2008 | 11/25/2008 | 11/25/2008 | A | PART |
Forrest France
|
|
|
1st floor wet system hydrostatic testing passed, plan resubmittals verified for changes at the overhead install for the first floor as well- okay for ceiling cover-see initialed area on plans.
|
CHANGE STATUS TO (ISS) | | | 11/24/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Case Summary | | | 11/24/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/20/2008 | | 11/20/2008 | | DONE |
|
|
|
|
Telephone call | | | 11/20/2008 | | DONE |
|
|
|
t/c w frank vigil at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 11/20/2008 | | DONE |
|
|
|
|
INSP-Supply line flush | 11/19/2008 | 11/19/2008 | 11/19/2008 | A | PART |
Forrest France
|
|
|
UG FDC piping flush completed acceptable.
|
INSP-Sprinkler Rough-in/Hydro | 11/19/2008 | 11/19/2008 | 11/19/2008 | A | PART |
Forrest France
|
|
|
Standpipe and remote FDC piping hydrostatic testing completed satisfactory.
|
Sprinkler Plan Check | 11/12/2008 | | 11/19/2008 | | PASS |
|
|
|
plans are approved
|
INSP-Supply line flush | 11/12/2008 | 11/13/2008 | 11/13/2008 | A | NR |
Forrest France
|
|
|
Underground fire department connection pipe flush postponed until repairs are made.
|
INSP-Sprinkler Rough-in/Hydro | 11/12/2008 | 11/13/2008 | 11/13/2008 | A | FAIL |
Forrest France
|
|
|
Hydrostatic testing for the remote FDC UG piping failed due to significant pressure loss at the guage.
|
Plan resubmittals received | | | 11/12/2008 | | |
Scott Arellano
|
|
|
received application & plans
|
INSP-Sprinkler Rough-in | 11/5/2008 | 11/5/2008 | 11/5/2008 | P | PART |
Forrest France
|
|
|
Remote FDC UG piping okayed for cover per resubmittals.
|
INSP-Sprinkler Rough-in/Hydro | 11/3/2008 | 11/4/2008 | 11/4/2008 | A | NR |
Forrest France
|
|
|
See inspection comments completed 10/6/08.
|
INSP-Sprinkler Rough-in/Hydro | 10/6/2008 | 10/6/2008 | 10/6/2008 | A | FAIL |
Forrest France
|
|
|
Inspection for the 1st floor failed due to field changes in pipe routing, head locations and floor plan layout in difference to the stamped approved plan set. Will need to provide accurate resubmittals for on site inspection prior to approval for ceiling cover.
|
CHANGE STATUS TO (ISS) | | | 9/22/2008 | | |
|
|
|
already issued previously
|
Permit Ready to Issue | | | 9/15/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 9/15/2008 | | DONE |
Cathy Brown
|
|
|
lft vm with frank vigil ###-#### that permit and fees are ready to be picked up
|
Inspection Record Card- Fire | 9/15/2008 | | 9/15/2008 | | DONE |
Cathy Brown
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/15/2008 | | DONE |
Cathy Brown
|
|
|
|
Sprinkler Plan Check | 9/8/2008 | | 9/14/2008 | | PASS |
|
|
|
This was the 4th review of these plans. Plans are approved w/conditions by Bryan Johnson
|
Plan resubmittals received | | | 9/8/2008 | | |
Sam Rogers
|
|
|
Received 3 copies of sheets 1-8, 1st page of app and cover transmittal in mail. Put in Fire bin
|
Plan resubmittals received | | | 7/29/2008 | | |
Sam Rogers
|
|
|
Plan Modification recieved on 7/15/08 and logged on to the wrong permit number Fir07-00928, and should have been submitted under this permit number per Sam Rogers. Plan mod was to relocate FDC pump tester//7/29/08 LEG
|
Sprinkler Plan Check | 7/29/2008 | | 7/29/2008 | | NR |
|
|
|
These plans for the Jefferson bldg. FDC & Pump Test Header (FIR07-01042) are on hold pending communication from the designer. The plan reviewer has requested that the designer, Frank Vigil of Fire Engineering contact him for project clarification. Please contact my office if you have any questions.
|
Telephone call | | | 7/29/2008 | | DONE |
|
|
|
telcon with BJ. All 8 sheets in Resubmitted package show a revision number but none show any clouding to identify the revised areas. Designer has not returned phone calls. Plans being held awaiting discussion with designer; a resubmittal may be required depending on explanation by the designer.
|
INSP-Sprinkler Rough-in/Hydro | 7/11/2008 | 7/14/2008 | 7/15/2008 | A | PART |
Forrest France
|
|
|
OH hydrostatic testing for the dry system passed, still need to complete 24 hr. air testing. Rough-in inspection for the parking garage levels PA 1, 2, 3, 4, and the storage areas also completed-see annotations on plan for defficiencies including spacing, head locations, head temp, etc.
|
FIR-Aging Inspection | 6/19/2008 | 6/19/2008 | 6/19/2008 | | DONE |
Forrest France
|
|
|
Work in progress, construction underway.
|
Telephone call | | | 4/7/2008 | | |
|
|
|
gave plans to customer- already paid fee ahead of time
|
Issue permit | | | 3/19/2008 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/7/2008 | | DONE |
|
|
|
|
Telephone call | | | 3/7/2008 | | DONE |
|
|
|
t/c w steve gaillard at ###-#### - permit ready and fees given
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/7/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/7/2008 | | 3/7/2008 | | DONE |
Patricia Smith
|
|
|
|
Sprinkler Plan Check | 2/25/2008 | | 3/5/2008 | | PASS |
|
|
|
plans are approved w/conditions as submitted by bryan johnson
|
Plan resubmittals received | | | 2/25/2008 | | |
|
|
|
|
Miscellaneous action | | | 2/14/2008 | | DONE |
|
|
|
The data has been moved to a Word document attached to this case.
|
Sprinkler Plan Check | 12/26/2007 | | 1/14/2008 | | FAIL |
|
|
|
These plans were denied due to lack of information and incomplete design. The plans will be separated into two separate permits under separate BLD numbers.
Upon request, the denied set may be retrieved from my office for salvage. The denied set will be maintained for 5 working days.
|
Application received | | | 12/26/2007 | | |
|
|
|
|
Pending Assignment by SAM | 12/26/2007 | | | | |
|
|
|
|
Plan assigned to (SAM) | 7/29/2008 | | | | |
|
|
|
|