Permit Information
Permit NumberFIR07-01051
StatusFinaled
Name ABSOLUTE FIRE PROTECTION
Site Address 5600 E WARM SPRINGS AVE
Project NameEAST JR HIGH SCHOOL
Customer Number 
ePlanReview 
Description
overhead and underground - Install new 6" Underground supply, 4 remote FDC line. Installation per NFPA 24 requiments.Scope of Work: Underground & Overhead
Beginning from an existing 6" stub in at the property line, run 90' of 6" C900 underground piping out and rise up into the bldg with 6" C-900 as indicated on sheet FP-1. A remote FDC will be installed including a 72' run of 4" C-900 to be buried in the same ditch as the 6" supply. The riser room of this new 120,805-ft/2 bldg. will be located on the North side of the structure. The over head portion of the project includes installing three wet pipe system risers to serve through out the bldg. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD07-01910
03/16/08 Plan Review Comments:
Plans were resubmitted to include the first floor piping plan and supporting calculations. The previous partially approved plans from 01/18/08 included the complete underground, riser detail and second floor piping only. Revisions to the underground have also been submitted for review with in this submittal dated 02/22/08. This review will be of a complete set of overhead and underground plans and supporting data.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/26/20095/26/20095/26/2009PPASS
DetailsForrest France
Fire sprinkler permit approved for final.
INSP-Final Inspection5/18/20095/18/20095/18/2009APART
DetailsForrest France
Fire sprinkler permit okayed for final when ceilings throughout are completed.
INSP-Final Inspection5/12/20095/13/20095/13/2009AFAIL
DetailsTroy Cobbley
Todays inspection covered the fire sprinkler device interconnections with the facp which passed. Also the forward flush passed. The sprinkler contractor is going to coordinate with the fire alarm contractor the riser descriptions so they match the what is listed on the facp. Ceiling tile was missing and the zone map has not been provided yet.
INSP-Final Inspection5/7/20095/8/20095/8/2009APART
DetailsForrest France
Walkthrough with contractor regarding items for final including ceiling finishes and escutcheons at some areas, zone map, signage at aux. drains, repaired flow switches and backflow certification done while on site, need to test riser supervision including flows and tampers in conjunction with fire alarm system when ready including account set up and monitoring, complete forward flow.
INSP-Sprinkler Rough-in/Hydro5/4/20095/5/20095/5/2009PPART
DetailsForrest France
Overhead hydrostatic testing completed for all three systems, inspection for cover at the locker rooms passed, re-inspection for corrections at the kitchen, hallway, stage and band rooms okayed.
INSP-Sprinkler Rough-in4/15/20094/16/20094/16/2009APASS
DetailsTroy Cobbley
See the city approved plans for locations where the sprinkler piping is ok for cover. These locations will have todays date and my initials.
INSP-Sprinkler Rough-in4/10/20094/13/20094/13/2009APART
DetailsForrest France
See locations on approved plan set sheet FP5 marked with today's date for ceilings okayed for cover and items in need of correction including two overspaced heads at the kitchen area, missing high temp. head at the storage room near the unit heater, one missing head at the vestibule to the wrestling room, re-pipe supply to one head in the hall, wrestling room ceiling okay for cover, NE classroom wing stairway 2nd floor also okay for cover.
INSP-Sprinkler Rough-in4/1/20094/2/20094/2/2009PPART
DetailsForrest France
See approved plans for overhead okayed for cover at drop ceilings 1st and 2nd floors various locations, also approved dry pendent install at the kitchen coolers.
INSP-Sprinkler Rough-in3/25/20093/25/20093/25/2009PPART
DetailsForrest France
Overhead rough-in at the boys and girls locker room sheetrock ceilings okayed for cover-see initials on shop drawings.
INSP-Sprinkler Rough-in3/23/20093/23/20093/25/2009PPART
DetailsForrest France
See plan annotations for areas inspected to date.
INSP-Sprinkler Rough-in3/19/20093/20/20093/20/2009PPART
DetailsForrest France
See plans marked with today's date for corridors and classrooms on the first and second floors inspected and okayed for cover, noted one overspaced head, discussed dry pendent locations at the coolers.
INSP-Sprinkler Rough-in3/12/20093/12/20093/12/2009PPART
DetailsForrest France
INSP-Sprinkler Rough-in3/6/20093/9/20093/9/2009PPART
DetailsForrest France
Rough-in inspection completed for the south gym (two covered heads and missing head guards), reinspection okayed for the office area defficiencies, band and choir rooms approved for cover, noted one overspaced head at the NE classroom wing common corridor, see plans for circled areas with today's date for locations okayed, main cpl. above the sheetrock ceiling at the band practice room to be repaired.
INSP-Sprinkler Rough-in3/5/20093/6/20093/6/2009APART
DetailsForrest France
Overhead install okay to cover except as noted at the 1st floor offices and cafeteria areas marked with todays date and initials, selected sheetrock ceilings need exposed for inspection and one overspaced head to be adjusted.
INSP-Sprinkler Rough-in2/25/20092/26/20092/26/2009APASS
DetailsTroy Cobbley
2nd Floor approved to cover except for 3 incomplete stairwells (stairwells highlighted on plans)
1st Floor bathrooms approved to cover and highlight on job site plans.
INSP-Sprinkler Rough-in2/24/20092/25/20092/25/2009APASS
DetailsTroy Cobbley
Mike and I agreed that tile will need to be removed on the second floor so that a rough-in inspection of the second floor piping can take place.
INSP-Sprinkler Rough-in2/23/20092/24/20092/25/2009ADONE
DetailsTroy Cobbley
The inspection was for the arm over/drops on the second floor. All of the arm over/drops are ok but it appears that a rough-in inspection for the main/branchline piping has not been performed. At this inspection I did not see a computer entry or markings on the plans indicating the inspection. Due to time limitations the fire sprinkler contractor is scheduling another inspection for tomorrow for a job site meeting to discuss this issue. I also found the second floor 2" west main did not have any earthquake bracing and a branchline located in the library had ceiling grid wire attached to it down its entire length.
INSP-Sprinkler Rough-in2/20/20092/20/20092/20/2009PDEFR
DetailsForrest France
mike Phone #: ###-####
INSP-Sprinkler Rough-in1/28/20091/29/20091/29/2009PPART
DetailsForrest France
Hangers at the locker room areas okayed for cover, 1st floor classroom wings east and south sides as marked on plans also okayed for cover, noted one missing ssu under the NE stairway and a pendent head at the "time out" room to be changed to an intermediate temp. due to proximity to a heat register.
Issue and Print Permit  1/6/2009 DONE
Sprinkler Plan Check1/2/2009 1/2/2009 PASS
DetailsTim Frost
No report attached. Simply reviewed the hydraulics to verify one butterfly valve had been added.
No annotations in the hydraulics
PLANS/APPL TAKEN TO FRONT DESK  1/2/2009 DONE
Inspection Record Card- Fire1/2/2009 1/2/2009 DONE
DetailsCathy Brown
Telephone call  1/2/2009 DONE
DetailsCathy Brown
lft vm with greg johnson ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  1/2/2009 DONE
DetailsCathy Brown
INSP-Sprinkler Rough-in12/15/200812/16/200812/16/2008APART
DetailsForrest France
Seismic attatchments at hangers for overhead piping at the mechanical mezzanine between gyms, the wrestling room/platform, and the south entry vestibule okayed. Also inspected piping to sidewall heads at three 2nd floor media area skylights -approved for cover.
INSP-Sprinkler Rough-in/Hydro12/1/200812/1/200812/1/2008PPART
DetailsForrest France
See approved plans for areas inspected to date.
INSP-Sprinkler Rough-in11/21/200811/24/200811/24/2008APART
DetailsTroy Cobbley
See the city approved plans for hanger locations, with todays date, that are ok to cover. I also did the rough-in inspection for the added sprinkler coverage in the mechanical closets between the restrooms on the first and second floors.
INSP-Sprinkler Rough-in11/21/200811/21/200811/24/2008PNH
DetailsForrest France
Rescheduled for 11/24 per discussion.
INSP-Sprinkler Rough-in11/7/200811/10/200811/10/2008APART
DetailsTroy Cobbley
See the city approved plans for hanger locations that are ok to cover. It has todays date and my signature.
INSP-Sprinkler Rough-in10/31/200810/31/200810/31/2008PPART
DetailsTroy Cobbley
See the city approved plans for locations where hanger attachments can be covered and sprinkler piping can be covered such as at both pairs of second floor restrooms.
INSP-Sprinkler Rough-in/Hydro10/21/200810/21/200810/21/2008PPART
DetailsForrest France
See locations on approved plans sheet FP5 and FP8 for the 1st floor electrical room and 2nd floor media center; hanger attatchments only approved for cover. NOTE: Hydrostatic testing for the underground supply line and remote FDC piping also completed and passed.
INSP-Supply line flush10/20/200810/21/200810/21/2008APART
DetailsForrest France
UG fire supply line and remote FDC piping flush completed acceptable.
INSP-Sprinkler Rough-in10/6/200810/7/200810/7/2008APART
DetailsForrest France
Overhead rough-in for areas D and E 1st floor as red lined with todays date are approved except as noted on plans sheet 6 and 7. Items include adding missing coverage at the mechanical room/chase between the restrooms, provide sway bracing at the end mains per NFPA 13 2007 9.3.5.3.4, noted two missing hangers, pipe hangers above hard lid ceilings below the stairways and at the mechanical room okayed.
INSP-Sprinkler Rough-in/Hydro9/15/20089/15/20089/15/2008PCANC
DetailsForrest France
Phone #: ###-####
INSP-Sprinkler Rough-in7/24/20087/24/20087/24/2008PNR
DetailsForrest France
wip
CHANGE STATUS TO (ISS)  3/19/2008 DONE
Issue and Print Permit  3/19/2008 DONE
Inspection Record Card- Fire3/18/2008 3/18/2008 DONE
DetailsCathy Brown
Plan assigned to (OutSourced)2/29/2008 3/18/2008 PASS
DetailsCathy Brown
3/18/2008 16:31:28 CMB - activity updated through activity FIRA22 from case FIR07-01051.
Inspection Record Card- Fire3/18/2008 3/18/2008 DONE
DetailsCathy Brown
PLANS/APPL TAKEN TO FRONT DESK  3/18/2008 DONE
Telephone call  3/18/2008 DONE
tlk to greg johnson ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  3/18/2008  
Sprinkler Plan Check2/29/2008 3/16/2008 PASS
Details
Plans & calculations are approved by Bryan Johnson
Plan resubmittals received  2/29/2008  
received "5" sets of plans & "5" hydraulic calculations with an application for each set- put plans on fire shelf
INSP-Sprinkler Rough-in2/20/20082/20/20082/20/2008PPART
DetailsForrest France
UG fire supply line and remote FDC piping are approved for bury, need to install caps at the risers and seismic clearance method at the floor slab penetrations.
Issue and Print Permit  2/11/2008 DONE
Sprinkler Plan Check2/6/2008 2/8/2008 PASS
Details
Quick Permit done by Bryan Johnson
PLANS/APPL TAKEN TO FRONT DESK  2/8/2008 DONE
Inspection Record Card- Fire2/8/2008 2/8/2008 DONE
DetailsCathy Brown
Telephone call  2/8/2008  
tlk to greg johnson ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  2/8/2008  
Sprinkler Plan Check1/18/2008 1/18/2008 PART
DetailsSam Rogers
Partial plans, only for UG and 2nd floor; reviewed and found acceptable by B. Johnson; 1st floor plans are to be submitted shortly, designer is awaiting architectural changes. These plans and permit will not be issued until the 1st flor plans are received and approved.
Sprinkler Plan Check12/28/2007 1/18/2008 PART
Details
Partial Approval Only. A complete resubmittal is required.
See plan review comments and conditions. by bryan johnson
Application received  12/28/2007  
Partial plans, only for UG and 2nd floor. 1st floor to be submitted shortly (architectural changes still being made)
Pending Assignment by SAM12/28/2007 12/28/2007  
Case Summary  12/28/2007 DONE
Plan assigned to (SAM)12/29/2008    
As built sent back to fire for review per Sam Rogers