Pending Assignment by SAM | 1/10/2008 | | 9/16/2008 | | DONE |
Cathy Brown
|
|
|
|
INSP-Final Inspection | 4/16/2008 | 4/17/2008 | 4/17/2008 | P | PASS |
Forrest France
|
|
|
Fire sprinkler work passed final inspection, permit finaled.
|
INSP-Sprinkler Rough-in | 3/11/2008 | 3/12/2008 | 3/12/2008 | P | PART |
Forrest France
|
|
|
See locations on approved plan set marked okay for cover at the lobby and elevator vestibules.
|
INSP-Sprinkler Rough-in | 2/14/2008 | 2/15/2008 | 2/15/2008 | A | PART |
Forrest France
|
|
|
Okayed cover at the hard lid ceilings for the elevator lobby- see area indicated on plans, also verified items from previous inspection.
|
INSP-Sprinkler Rough-in | 2/5/2008 | 2/6/2008 | 2/6/2008 | P | PART |
Forrest France
|
|
|
See red-lined areas on city stamped plan set for overhead rough-in locations approved for cover, noted two heads at the entry vestibule to be changed to QR, and two drops not yet installed.
|
Issue and Print Permit | | | 1/25/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/24/2008 | | 1/24/2008 | | DONE |
Patricia Smith
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/24/2008 | | DONE |
|
|
|
|
Telephone call | | | 1/24/2008 | | DONE |
|
|
|
t/c w brad bettencourt at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 1/24/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/10/2008 | | 1/22/2008 | | PASS |
|
|
|
plans are approved as submitted by bryan johnson
|
Application received | | | 1/10/2008 | | |
|
|
|
|
Case Summary | | | 1/10/2008 | | DONE |
|
|
|
|