INSP-Final Inspection | 3/27/2008 | 3/28/2008 | 3/28/2008 | A | PASS |
Forrest France
|
|
|
One defective sprinkler head at an office replaced immediately on site by R. Fry, remainder of fire sprinkler work passed inspection, permit finaled.
|
INSP-Sprinkler Rough-in | 1/30/2008 | 1/30/2008 | 1/30/2008 | P | PART |
Forrest France
|
|
|
OH rough-in inspection completed, attatchments and installation appears acceptable however final head location cannot be approved at this time due to lacking walls at all areas which are not yet constructed at this time.
|
Issue and Print Permit | | | 1/16/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/15/2008 | | 1/15/2008 | | PASS |
Scott Arellano
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/15/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/15/2008 | | 1/15/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 1/15/2008 | | DONE |
|
|
|
lft vm with brodie stienquist ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 1/15/2008 | | DONE |
|
|
|
|
Application received | | | 1/14/2008 | | |
|
|
|
|
Pending Assignment by SAM | 1/14/2008 | | | | |
|
|
|
|