Miscellaneous action | | | 3/10/2009 | | DONE |
|
|
|
Sending for archiving
|
INSP-Final Inspection | 3/9/2009 | 3/9/2009 | 3/9/2009 | P | PASS |
Forrest France
|
|
|
Corrections completed, fire sprinkler permit finaled.
|
Override - Parcel Holds | 3/9/2009 | 1/1/1900 | 3/9/2009 | | |
|
|
|
fire sprinkler
|
INSP-Final Inspection | 2/5/2009 | 2/6/2009 | 2/6/2009 | A | NH |
Forrest France
|
|
|
Ryan is the contact. Thanks Phone #: ###-#### Internet Inspection Request from: Stan Beus
|
INSP-Final Inspection | 2/4/2009 | 2/5/2009 | 2/5/2009 | A | PART |
Forrest France
|
|
|
Need as-built plans prior to permit final.
|
INSP-Final Inspection | 1/9/2009 | 1/12/2009 | 1/12/2009 | P | FAIL |
Forrest France
|
|
|
Four missing escutcheons, basement level storage room 001 has not been sprinklered.
|
INSP-Sprinkler Rough-in/Hydro | 12/5/2008 | 12/5/2008 | 12/5/2008 | P | PART |
Forrest France
|
|
|
Rough-in okayed for cover.
|
INSP-Sprinkler Rough-in | 10/16/2008 | 10/17/2008 | 10/17/2008 | P | PART |
Forrest France
|
|
|
Previous c/n items for the overhead rough-in have been corrected, install is okay for cover when main tie-ins have been finished.
|
INSP-Sprinkler Rough-in/Hydro | 10/16/2008 | 10/16/2008 | 10/16/2008 | A | PART |
Forrest France
|
|
|
Hydrostatic test for the wet and antifreeze systems east remodel area syst. #2 completed acceptable.
|
INSP-Sprinkler Rough-in/Hydro | 10/14/2008 | 10/15/2008 | 10/16/2008 | P | FAIL |
Forrest France
|
|
|
Need to add coverage at one closet and adjust spacing at one location in the attic-see plans for annotations.
|
INSP-Final Inspection | 5/27/2008 | 5/27/2008 | 5/27/2008 | P | NR |
Forrest France
|
|
|
Permit work is not yet completed for final approval, system riser #2 feeding the east remodel is not in service as rough-in is not finished, riser #1 supervisory and alarm system interconnection tested okay-fire sprinkler install for work completed to date for "phase 1" appears acceptable.
|
INSP-Final Inspection | 5/22/2008 | 5/23/2008 | 5/23/2008 | A | CANC |
Forrest France
|
|
|
Mike B is the contact. Thanks Phone #: ###-#### Internet Inspection Request from: Stan Beus Overbooked, inspection rescheduled per phone call to contractor.
|
INSP-Sprinkler Rough-in/Hydro | 4/3/2008 | 4/4/2008 | 4/4/2008 | A | DONE |
Forrest France
|
|
|
Overhead hydro completed, passed.KR
|
INSP-Sprinkler Rough-in | 3/28/2008 | 3/31/2008 | 3/31/2008 | A | DONE |
Forrest France
|
|
|
OK to cover in mens and womans restrooms.Changes complete per Forrest last inspection. KR
|
INSP-Sprinkler Rough-in | 3/26/2008 | 3/27/2008 | 3/27/2008 | A | FAIL |
Forrest France
|
|
|
One upright head at the womens restroom is blocked by adjacent ductwork, one ssu at the mens restroom is obstructed by the top joist cord which extends below and directly next to the deflector, missing EQ brace at the last piece of main. Areas approved for cover include the hall 116, sacristy 115, and the narthex entry 101-see stamped plans for initialed locations. Also verified resubmittals match installation at areas where field modifications were done.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/26/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/26/2008 | | 3/26/2008 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 3/26/2008 | | DONE |
|
|
|
left message w antoinette for lillie at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 3/26/2008 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/26/2008 | | DONE |
|
|
|
|
(F) Reprint permit | | | 3/26/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/20/2008 | | 3/25/2008 | | PASS |
|
|
|
as-built plans are approved w/conditions
|
Plan resubmittals received | | | 3/20/2008 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 3/3/2008 | 3/4/2008 | 3/4/2008 | A | FAIL |
Forrest France
|
|
|
Provide plan resubmittals reflecting field modifications and installation of CPVC piping for several branchlines.
|
Permit Ready to Issue | | | 2/7/2008 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/7/2008 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/6/2008 | | DONE |
|
|
|
|
Telephone call | | | 2/6/2008 | | |
|
|
|
tlk to lilly scales ###-#### that permit and fees are ready to be picked up
|
Inspection Record Card- Fire | 2/6/2008 | | 2/6/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 2/5/2008 | | DONE |
|
|
|
The following email was sent to Shilo and B. Johnson in response to a telephone request from Lillie today.
"This is to confirm that we will accept these plans to be designed under the 2002 ed of NFPA 13. This is because we have confirmed that the design calc's were done in December but apparently the plans inadvertently were delivered to a wrong address on 12/13/07 per the courier's signed cover sheet, and therefore were not delivered to Boise PDS until Jan 16, 2008.
Regards,
Sam"
|
Application received | | | 1/16/2008 | | |
|
|
|
|
Sprinkler Plan Check | 1/16/2007 | | 2/6/2007 | | PASS |
|
|
|
Plans are approved w/conditions by Bryan Johnson
|