DOC - Permit Finaled | | | 4/4/2008 | | DONE |
|
|
|
final inspection passed 3/27/08
|
INSP-Final Inspection | 3/26/2008 | 3/27/2008 | 3/27/2008 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit final inspection passed.
|
INSP-Sprinkler Rough-in/Hydro | 2/26/2008 | 2/27/2008 | 2/27/2008 | A | PART |
Forrest France
|
|
|
Overhead rough-in is approved for cover at the NE quad as red-lined on stamped plans, one ret. strap attatched while on site, OH hydrostatic test completed in conjunction also passed.
|
INSP-Sprinkler Rough-in/Hydro | 2/8/2008 | 2/11/2008 | 2/11/2008 | A | PART |
Forrest France
|
|
|
OH rough-in installation passed inspection, see annotations on plan with today's date, hydrostatic testing for this remodel area also completed acceptable.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/8/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/8/2008 | | 2/8/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 2/8/2008 | | DONE |
|
|
|
tlk to tom householder 1-###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 2/8/2008 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/8/2008 | | |
|
|
|
|
Sprinkler Plan Check | 1/22/2008 | | 2/6/2008 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Case Summary | | | 1/22/2008 | | DONE |
|
|
|
|
Application received | | | 1/22/2008 | | |
|
|
|
|
Pending Assignment by SAM | 1/22/2008 | | | | |
|
|
|
|