INSP-Final Inspection | 3/20/2008 | 3/20/2008 | 3/20/2008 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Supply line flush | 2/25/2008 | 2/25/2008 | 2/25/2008 | P | PASS |
Troy Cobbley
|
|
|
The underground flush passed.
|
Miscellaneous action | | | 2/19/2008 | | DONE |
|
|
|
The application for a building permit for this project has been denied due to zoning conflict. The matter is being addressed by the building owner and planning and zoning.
|
INSP-Sprinkler Rough-in/Hydro | 2/6/2008 | 2/6/2008 | 2/6/2008 | P | PASS |
Troy Cobbley
|
|
|
The undergrond supply pipe is ok to be buried. This the only item inspected today.
|
Issue and Print Permit | | | 2/1/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/29/2008 | | 1/30/2008 | | PASS |
Scott Arellano
|
|
|
|
Plan resubmittals received | | | 1/30/2008 | | DONE |
|
|
|
Manufacturers product listing delivered by fire sprinkler designer.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/30/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/30/2008 | | 1/30/2008 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 1/30/2008 | | DONE |
|
|
|
left message w laura for ben chavez at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 1/30/2008 | | DONE |
|
|
|
|
Telephone call | | | 1/29/2008 | | DONE |
|
|
|
Requested addtional information regarding the specific listing of the CPVC pipe material to be used in an underground application. Matt Kahn is sending requested information.
|
Case Summary | | | 1/28/2008 | | |
|
|
|
|
Application received | | | 1/28/2008 | | |
|
|
|
|
Pending Assignment by SAM | 1/28/2008 | | | | |
|
|
|
|