INSP-Final Inspection | 4/24/2008 | 4/25/2008 | 4/25/2008 | A | PASS |
Forrest France
|
|
|
Noted corrections are complete, fire sprinkler work passed inspection, permit finaled.
|
INSP-Sprinkler Rough-in | 4/7/2008 | 4/7/2008 | 4/7/2008 | P | PART |
Forrest France
|
|
|
All corrections made per Forrest notes.OK to cover all areas except the reception desk at the southeast office.See redline on city approved plans.KR
|
INSP-Sprinkler Rough-in | 3/21/2008 | 3/24/2008 | 3/24/2008 | A | FAIL |
Forrest France
|
|
|
Heads at two areas are overspaced including the vestibule and one storage room-see plans for locations, also need to plug the outlet used for an auxillary drain above the ceiling, heads at the room marked "file storage" are overspaced per room usage-verify use or provide coverage per plan.
|
INSP-Sprinkler Rough-in | 3/5/2008 | 3/5/2008 | 3/5/2008 | P | PART |
Forrest France
|
|
|
See approved plans for areas initialed with today's date okayed for cover at the hard lid ceilings for the east remodel area.
|
INSP-Sprinkler Rough-in | 2/21/2008 | 2/21/2008 | 2/21/2008 | P | PART |
Forrest France
|
|
|
Ok to cover electrical room, see red lined notes on approved city plans. KR
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/15/2008 | | DONE |
|
|
|
|
Telephone call | | | 2/15/2008 | | DONE |
|
|
|
tlk to jim heiller ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 2/15/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/15/2008 | | 2/15/2008 | | DONE |
Cathy Brown
|
|
|
|
Issue and Print Permit | | | 2/15/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/28/2008 | | 2/14/2008 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Application received | | | 1/28/2008 | | |
|
|
|
|
Pending Assignment by SAM | 1/28/2008 | | | | |
|
|
|
|