INSP-Final Inspection | 3/20/2008 | 3/20/2008 | 3/20/2008 | P | PASS |
Troy Cobbley
|
|
|
permit passed
|
Issue and Print Permit | | | 3/20/2008 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 3/7/2008 | | 3/19/2008 | | PASS |
Cathy Brown
|
|
|
3/19/2008 16:24:45 CMB - activity updated through activity FIRA22 from case FIR08-00085.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/19/2008 | | |
|
|
|
|
Telephone call | | | 3/19/2008 | | DONE |
|
|
|
tlk to secretary ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 3/19/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/19/2008 | | 3/19/2008 | | DONE |
Cathy Brown
|
|
|
|
Sprinkler Plan Check | 3/7/2008 | | 3/18/2008 | | PASS |
|
|
|
*As built Plans & calculations are approved by Bryan Johnson
|
INSP-Sprinkler Rough-in | 3/12/2008 | 3/12/2008 | 3/12/2008 | P | PASS |
Troy Cobbley
|
|
|
The piping can be covered by the deco shield.
|
INSP-Sprinkler Rough-in | 3/7/2008 | 3/7/2008 | 3/7/2008 | P | PASS |
Troy Cobbley
|
|
|
The tenting inspection is passed. The sprinkler piping can be covered with the blow-in insulation.
|
Plan resubmittals received | | | 3/7/2008 | | |
|
|
|
Plan modification submitted: received application, four books of submittal info and four copies of sheets FP1; taken to fire review
|
INSP-Sprinkler Rough-in | 2/25/2008 | 2/25/2008 | 2/25/2008 | P | PART |
Troy Cobbley
|
|
|
Rough-in inspection passed. Plans are being resubmitted as per Ben due to sprinkler heads being changed which is effecting the K factor. Piping in the kitchen wall can be covered. A tenting inspection will be required prior to covering with insulation.
|
Issue and Print Permit | | | 2/21/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/20/2008 | | |
|
|
|
|
Inspection Record Card- Fire | 2/20/2008 | | 2/20/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 2/20/2008 | | DONE |
|
|
|
lft ms with secretary for ben chavez ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 2/20/2008 | | DONE |
|
|
|
|
Miscellaneous action | | | 2/19/2008 | | DONE |
|
|
|
The application for a building permit for this project has been denied due to zoning conflict. The matter is being addressed by the building owner and planning and zoning.
|
Sprinkler Plan Check | 2/1/2008 | | 2/17/2008 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Application received | | | 2/1/2008 | | |
|
|
|
|
Pending Assignment by SAM | 2/1/2008 | | | | |
|
|
|
|