Miscellaneous action | | | 10/26/2009 | | DONE |
|
|
|
Fire alarm plans taken to records
|
INSP-Final Inspection | 10/1/2009 | 10/2/2009 | 10/2/2009 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Override - Parcel Holds | | | 7/23/2009 | | |
|
|
|
|
Inspection Record Card- Fire | 7/23/2009 | | 7/23/2009 | | DONE |
|
|
|
|
Telephone call | | | 7/23/2009 | | DONE |
|
|
|
t/c w robert gobler at ###-#### - permit (plan mod) ready and fees given
|
Override - Parcel Holds | | | 7/23/2009 | | |
|
|
|
|
Permit Ready to Issue | | | 7/23/2009 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/23/2009 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/23/2009 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 7/21/2009 | | 7/22/2009 | | DONE |
Stephanie L. Cobbley
|
|
|
7/22/2009 16:20:48 SLC - activity updated through activity FIRA24 from case FIR08-00094.
|
Alarm Plan Check | 7/22/2009 | | 7/22/2009 | | PASS |
Stephanie L. Cobbley
|
|
|
Approveed with no review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 7/22/2009 | | DONE |
|
|
|
Approved plans available at front counter. No review comments
|
Plan resubmittals received | | | 7/21/2009 | | |
Stephanie L. Cobbley
|
|
|
|
INSP-Alarm Testing | 4/27/2009 | 4/28/2009 | 4/28/2009 | A | PASS |
Troy Cobbley
|
|
|
The alarm system for the remaining area of the Assisted Living is complete. Resubmittals are required showing all of the changes which include wall layout changes. Robert will provide a printout of the test reports.
|
INSP-Sprinkler Rough-in/Hydro | 4/27/2009 | 4/27/2009 | 4/27/2009 | P | CANC |
Forrest France
|
|
|
Overbooked
|
INSP-Alarm Testing | 4/23/2009 | 4/24/2009 | 4/24/2009 | A | DEFR |
Forrest France
|
|
|
Overbooked, rescheduled per phone conversation.
|
INSP-Alarm Testing | 12/11/2008 | 12/12/2008 | 12/12/2008 | P | PART |
Troy Cobbley
|
|
|
The new Dining Room and the Aid Station areas fire alarm is complete and functional.
|
INSP-Alarm Testing | 6/19/2008 | 6/19/2008 | 6/19/2008 | P | DONE |
Troy Cobbley
|
|
|
The fire door operated correctly at the junction point of the new ten room addition and the existing facility. This completes the fire alarm in the west two room addition and the ten room addition.
|
INSP-Alarm Testing | 6/5/2008 | 6/6/2008 | 6/6/2008 | P | DONE |
Troy Cobbley
|
|
|
Partial Inspection. Todays inspection was for the new north wing addition and the new south wing addition. Everything tested satifactory except the fire doors in the south wing were not ready to be tested yet.
|
INSP-Alarm Testing | 6/5/2008 | 6/6/2008 | 6/5/2008 | A | CANC |
Troy Cobbley
|
|
|
Customer looking for temp CO. Phone #: ###-#### Internet Inspection Request from: Robert Gobler Inspection cancelled from web by: Robert Gobler
|
FIR-Aging Inspection | 6/2/2008 | 6/2/2008 | 6/2/2008 | | NR |
Troy Cobbley
|
|
|
work is in progress
|
Issue and Print Permit | | | 3/3/2008 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/29/2008 | | PASS |
|
|
|
See fire plan review notes for comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/29/2008 | | |
|
|
|
|
Inspection Record Card- Fire | 2/29/2008 | | 2/29/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 2/29/2008 | | DONE |
|
|
|
lft vm with robert gobler ###-#### that permit and no fees are ready to be picked up
|
Permit Ready to Issue | | | 2/29/2008 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 2/20/2008 | | 2/20/2008 | | DONE |
Cathy Brown
|
|
|
|
Sprinkler Plan Check | 2/4/2008 | | 2/20/2008 | | FAIL |
Kenneth R Roule
|
|
|
failed per ken r.
|
Telephone call | | | 2/20/2008 | | DONE |
|
|
|
t/c w robert gobler at ###-#### - permit needs to be picked up - failed by ken r. - double fee amout given
|
Plan assigned to (Mike) | 2/4/2008 | | 2/13/2008 | | FAIL |
Kenneth R Roule
|
|
|
Double fee. Started work without a permit.Fax a copy of plan review report to fire alarm designer .
|
Case Summary | | | 2/4/2008 | | DONE |
|
|
|
|
Application received | | | 2/4/2008 | | |
|
|
|
|