Miscellaneous action | | | 5/8/2009 | | DONE |
|
|
|
plans taken to records for scanning
|
INSP-Final Inspection | 3/19/2009 | 3/20/2009 | 3/20/2009 | A | PASS |
Forrest France
|
|
|
Fire alarm permit approved for final.
|
Plan assigned to (Forrest) | 3/16/2009 | | 3/16/2009 | | DONE |
Forrest France
|
|
|
|
Alarm Plan Check | 3/16/2009 | | 3/16/2009 | | PASS |
|
|
|
Modified plans by R. Gobler approved per "red lined" plan annotations. No written comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/16/2009 | | DONE |
|
|
|
|
Telephone call | | | 3/16/2009 | | DONE |
|
|
|
left vm for robert gobler at ###-#### - permit ready to be picked (resubmittal)
|
Permit Ready to Issue | | | 3/16/2009 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/16/2009 | | 3/16/2009 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/16/2009 | | DONE |
|
|
|
|
(F) Reprint permit | | | 3/16/2009 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 2/25/2009 | | 3/9/2009 | | PEND |
Sam Rogers
|
|
|
3/9/09 - Met with Rober Guler and discussed plan discrepancies and omissions. He will make annotated corrections in "red" with his initials on all plan sets at the plan desk here in the PDS office and and return the corrected plans to the permit counter. Plans left at the front counter for him to obtain later this afternoon to make corrections.
|
Plan resubmittals received | | | 2/25/2009 | | |
|
|
|
Plan modification: Received application, three copies of submittal info binder, and plan sheets F0.0, F1.0, F1.1, F1.2, F1.3, F1.4, F1.5, F1.6, F1.7, F2.0 taken to Fire Review
|
INSP-Alarm Testing | 2/24/2009 | 2/24/2009 | 2/24/2009 | P | DONE |
Troy Cobbley
|
|
|
TRASH ROOM SMOKE DETECTOR Phone #: ###-#### Internet Inspection Request from: Robert Gobler
|
INSP-Alarm Testing | 2/24/2009 | 2/24/2009 | 2/24/2009 | A | DONE |
Scott Arellano
|
|
|
Tested smoke door operation at exterior wall, located in garbage room. Tested satisfactory.
|
INSP-Final Inspection | 2/20/2009 | 2/20/2009 | 2/20/2009 | P | PART |
Forrest France
|
|
|
Remainder of fire alarm testing completed satisfactory, noted corrections have been finished, elevator, FACP, balance of notification, etc. all tested okay. Final pending one SD for door release at the trash room level P1 to be tested (missing power to overhead door), and provision of resubmittal plans for field modifications including added ID detectors, hoistway devices, deleted points, accurate matrix, etc. as discussed.
|
INSP-Alarm Testing | 2/11/2009 | 2/12/2009 | 2/12/2009 | A | PART |
Forrest France
|
|
|
Discussed plan resubmittals due to modifications including 13 added SD for dampers in the common corridors, added heat and smoke detectors in the elevator hoistway, relay for the mag locks at the main lobby doors, changes in the matrix for unused CR at the elevator smoke doors. Walkthrough for the basement level parking garage completed-noted one overspaced area at a handicap accessible parking space. Discussed project inspection schedule, also need to provide list of signals recieved during pre-testing.
|
FIR-Aging Inspection | 5/30/2008 | 5/30/2008 | 5/30/2008 | | DONE |
Forrest France
|
|
|
Under construction, work in progress.
|
Issue and Print Permit | | | 2/28/2008 | | |
|
|
|
|
Plan assigned to (Mike) | 2/6/2008 | | 2/25/2008 | | PASS |
Kenneth R Roule
|
|
|
See review notes for comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/25/2008 | | |
|
|
|
|
Inspection Record Card- Fire | 2/25/2008 | | 2/25/2008 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 2/25/2008 | | DONE |
|
|
|
t/c w robert gobler at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 2/25/2008 | | DONE |
|
|
|
|
Case Summary | | | 2/6/2008 | | |
|
|
|
|
Application received | | | 2/6/2008 | | |
|
|
|
|