INSP-Final Inspection | 6/4/2008 | 6/4/2008 | 6/4/2008 | P | PASS |
Forrest France
|
|
|
Noted defficiencies verified for correction, fire sprinkler final inspection passed.
|
INSP-Final Inspection | 5/28/2008 | 5/29/2008 | 5/29/2008 | A | FAIL |
Forrest France
|
|
|
Defficiencies noted include missing stock of ESFR heads at the riser head box, overspaced upright heads at the new grade level riser room, 3 branchlines at the warehouse area are too low for pendent ESFR head listing, pendent heads at the office storage room and men's restroom are obstructed by surface mounted lights, DP at the cooler condensers have been added.
|
INSP-Final Inspection | 5/27/2008 | 5/28/2008 | 5/28/2008 | P | CANC |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 5/27/2008 at 4:28:25 PM. Contact: ###-####. Overbooked
|
INSP-Final Inspection | 5/20/2008 | 5/21/2008 | 5/21/2008 | A | NR |
Forrest France
|
|
|
rod Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 5/20/2008 | 5/21/2008 | 5/21/2008 | A | PART |
Forrest France
|
|
|
Hydrostatic test for the east office area remodel and addition passed.
|
INSP-Final Inspection | 4/1/2008 | 4/2/2008 | 4/2/2008 | P | PART |
Forrest France
|
|
|
Installed approx 10 trim rings in the new spirit offices. No other inspection performed under this permit. KR
|
INSP-Sprinkler Rough-in | 3/13/2008 | 3/14/2008 | 3/14/2008 | P | PART |
Forrest France
|
|
|
Sprinkler rough-in at the office area hard lid ceilings is approved for cover, noted one head to be installed under the stairway combustible concealed space, sidewinder sammy screws for hanger attatchments must be installed per manufacturers listing requirements, new DP heads at the beer cooler are acceptable as installed pending the addition of three heads where refrigeration units block coverage. NOTE: The existing ESFR upright heads at the warehouse area have been compromised by the placement of new insulation and backing at the roof deck resulting in sprinkler obstruction and violation of the head listing, permit will not be finaled until this situation is corrected.
|
Issue permit | | | 3/5/2008 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/3/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/3/2008 | | 3/3/2008 | | DONE |
Cathy Brown
|
|
|
|
Permit Ready to Issue | | | 3/3/2008 | | DONE |
|
|
|
|
Telephone call | | | 3/3/2008 | | DONE |
|
|
|
tlk to jim danes of americna fire ###-#### that permit and fees are ready to be picked up
|
Sprinkler Plan Check | 2/14/2008 | | 2/28/2008 | | PASS |
|
|
|
Plans and calculations are approved by Bryan Johnson
|
Application received | | | 2/14/2008 | | |
|
|
|
|
Case Summary | | | 2/14/2008 | | |
|
|
|
|
Pending Assignment by SAM | 2/14/2008 | | | | |
|
|
|
|