INSP-Final Inspection | 10/13/2008 | 10/14/2008 | 10/14/2008 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 7/22/2008 | 7/23/2008 | 7/23/2008 | A | PASS |
Troy Cobbley
|
|
|
UG hydro test passed.
|
INSP-Sprinkler Rough-in | 7/18/2008 | 7/22/2008 | 7/22/2008 | A | PASS |
Troy Cobbley
|
|
|
UG flush passed
|
INSP-Sprinkler Rough-in | 3/7/2008 | 3/10/2008 | 3/10/2008 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line is ok to cover.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/28/2008 | | DONE |
|
|
|
|
Telephone call | | | 2/28/2008 | | DONE |
|
|
|
lft ms with secretary for gerald ebeling ###-#### that permit and fees are ready to be picked up
|
Inspection Record Card- Fire | 2/28/2008 | | 2/28/2008 | | DONE |
Cathy Brown
|
|
|
|
Permit Ready to Issue | | | 2/28/2008 | | |
|
|
|
|
Issue and Print Permit | | | 2/28/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/21/2008 | | 2/25/2008 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Application received | | | 2/21/2008 | | |
|
|
|
|
Pending Assignment by SAM | 2/21/2008 | | | | |
|
|
|
|