Miscellaneous action | | | 5/8/2009 | | DONE |
|
|
|
plans taken to records for scanning
|
INSP-Final Inspection | 8/20/2008 | 8/20/2008 | 8/20/2008 | P | PASS |
Forrest France
|
|
|
items on correction notice verified for completion, fire alarm permit finaled.
|
INSP-Alarm Testing | 8/19/2008 | 8/19/2008 | 8/19/2008 | A | FAIL |
Forrest France
|
|
|
Fire alarm system field testing completed however reciept of signals could not be verifed due to lack of account monitoring set up, need to complete NFPA 72 inspection and testing forms including a list of singals prior to final, provide plans reflecting field changes including deleted notification devices, deleted elevator hoistway detectors, changed battery to 18 AH, provide accurate map at the panel, post signage at the door to the FACP room, change descriptor at riser #2 to read "antifreeze system", need to test main door mag lock interconnection to the fire alarm when finished.
|
INSP-Alarm Testing | 8/15/2008 | 8/18/2008 | 8/18/2008 | P | FAIL |
Forrest France
|
|
|
Elevator is not yet completed to verify fire alarm interconnections and functionality.
|
FIR-Aging Inspection | 6/20/2008 | 6/20/2008 | 6/20/2008 | | DONE |
Forrest France
|
|
|
wip
|
Issue permit | | | 3/21/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/20/2008 | | 3/20/2008 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 3/20/2008 | | DONE |
|
|
|
left vm for john schmidt at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 3/20/2008 | | DONE |
|
|
|
|
Plan assigned to (Mike) | 2/21/2008 | | 3/18/2008 | | PASS |
Kenneth R Roule
|
|
|
3/18/2008 15:43:04 KRR - activity updated through activity FIRA22 from case FIR08-00151.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/18/2008 | | |
|
|
|
|
Application received | | | 2/21/2008 | | |
|
|
|
|
Case Summary | | | 2/21/2008 | | DONE |
|
|
|
|