INSP-Final Inspection | 6/2/2008 | 6/2/2008 | 6/2/2008 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
|
INSP-Final Inspection | 5/30/2008 | 6/3/2008 | 6/2/2008 | P | CANC |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 5/30/2008 at 4:48:42 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Jun 2 2008 7:49AM.
|
INSP-Final Inspection | 5/29/2008 | 5/30/2008 | 5/30/2008 | A | DEFR |
Forrest France
|
|
|
|
INSP-Final Inspection | 5/28/2008 | 5/29/2008 | 5/29/2008 | A | NR |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 5/28/2008 at 3:15:38 PM. Contact: ###-####.
|
INSP-Final Inspection | 5/27/2008 | 5/28/2008 | 5/28/2008 | P | CANC |
Forrest France
|
|
|
rod Phone #: ###-#### Overbooked
|
INSP-Sprinkler Rough-in/Hydro | 5/6/2008 | 5/7/2008 | 5/7/2008 | A | PART |
Forrest France
|
|
|
OH install at the east office area first and second floors for rooms and areas completed to date are okay for cover, no access at one hallway due to flooring work underway, missing heads at two utility rooms 2nd floor, verified corrections are finished at the entry vestibule, need access to verify coverage at the concealed combustible spaces under the stairway at two locations. Hydrostatic testing for the new 10"supply main at the warehouse completed satisfactory, also discussed seismic bracing issues.
|
INSP-Sprinkler Rough-in/Hydro | 5/5/2008 | 5/6/2008 | 5/7/2008 | P | CANC |
Forrest France
|
|
|
Overbooked
|
INSP-Sprinkler Rough-in/Hydro | 4/29/2008 | 4/29/2008 | 4/29/2008 | A | NR |
Forrest France
|
|
|
New supply line pipe hydrostatic test is not ready for inspection due to leakage per contractor, also okayed areas as red-lined on approved plan set at the front office entry hard lids-noted three ret. straps to be attatched and one head to be relocated for correct min. spacing requirements.
|
INSP-Sprinkler Rough-in/Hydro | 4/25/2008 | 4/28/2008 | 4/28/2008 | P | FAIL |
Forrest France
|
|
|
Hydrostatic testing for the new 10" supply line failed due to pressure loss at the guage and visible leakage at OS&Y isolation valves, also noted system static is approx. 165 psi which will necessitate testing in excess of 200 psi to meet NFPA requirements.
|
INSP-Sprinkler Rough-in/Hydro | 4/8/2008 | 4/9/2008 | 4/9/2008 | P | FAIL |
Forrest France
|
|
|
Inspection for cover at the womens and mens restrooms for the office area east side failed due to two pendent sprinkler heads which do not meet obstruction tables per NFPA 13.
|
Issue permit | | | 4/7/2008 | | |
|
|
|
|
Inspection Record Card- Fire | 4/4/2008 | | 4/4/2008 | | DONE |
Patricia Smith
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/4/2008 | | DONE |
|
|
|
|
Telephone call | | | 4/4/2008 | | DONE |
|
|
|
left vm for jim danes at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 4/4/2008 | | DONE |
|
|
|
|
Plan assigned to (OutSourced) | 3/5/2008 | | 4/4/2008 | | PASS |
Patricia Smith
|
|
|
4/4/2008 13:12:11 P_S - activity updated through activity FIRA22 from case FIR08-00180.
|
Sprinkler Plan Check | 3/25/2008 | | 3/31/2008 | | PASS |
|
|
|
plans & calculations are approved w/conditions
|
Plan resubmittals received | | | 3/25/2008 | | |
|
|
|
|
Case Summary | | | 3/25/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/5/2008 | | 3/24/2008 | | FAIL |
|
|
|
These plans were denied as a result of a failed field inspection of the existing ESFR system. Upon request, the denied set of plans maybe retrieved from my office for salvage. The denied set will be maintained for 5 working days.
|
Case Summary | | | 3/5/2008 | | DONE |
|
|
|
|
Application received | | | 3/5/2008 | | |
|
|
|
|
Pending Assignment by SAM | 3/5/2008 | | | | |
|
|
|
|