INSP-Final Inspection | 6/25/2008 | 6/26/2008 | 6/26/2008 | A | PASS |
Forrest France
|
|
|
Fire sprinkler testing complete. KR
|
INSP-Sprinkler Rough-in | 5/28/2008 | 5/29/2008 | 5/29/2008 | A | PASS |
Troy Cobbley
|
|
|
The underground piping can be buried and it has also been flushed.
|
INSP-Sprinkler Rough-in | 4/17/2008 | 4/21/2008 | 4/21/2008 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping rough-in is passed. The insulation needs to be installed over the piping in the new addition and inspected. The tenting needs to be performed over the piping in the existing section and inspected.
|
Issue and Print Permit | | | 4/14/2008 | | |
|
|
|
|
Inspection Record Card- Fire | 4/10/2008 | | 4/10/2008 | | DONE |
Patricia Smith
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/10/2008 | | DONE |
|
|
|
|
Telephone call | | | 4/10/2008 | | DONE |
|
|
|
t/c w john warnick at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 4/10/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/25/2008 | | 4/9/2008 | | PASS |
|
|
|
plans are approved
|
Early Start | | | 4/4/2008 | | FAIL |
|
|
|
Denied a request to install so they can continue with "interior finish" work via email to Brook at Commercial Fire. It is necessary to conduct a rough-in inspection prior to cover, so no finish/cover work is allowed proceed until after an approved rough in inspection. Approved plans need to be on site at the time of the inspection.
|
Application received | | | 3/25/2008 | | |
|
|
|
|
Pending Assignment by SAM | 3/25/2008 | | | | |
|
|
|
|