Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberFIR08-00228
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 250 E PARKCENTER BLVD
Project NameSUPERVALU -PHASE 2
Customer Number 
ePlanReview 
Description
Work Scope: (SUPERVALU - PHASE 2) -(2nd Floor) (SIX SIGMA & IMW) To remodel a 31,557 sq ft portion of the second story located in the southwest corner of the building for office tenant per approved plans. Work to include, selective demolition of interior nonbearing partitions, construction of new partitions for private office spaces, small conference rooms, and open office area, repair and relocate existing suspended ceiling and lighting, relocate any diffusers as necessary, this building is fully fire sprinklered for unlimited area any alterations to the sprinkler system shall be per NFPA #13 as regulated by the fire department. **(PLAN MODIFICATION)**(3-31-08)** To reconfigure office layout, and open office area from the original layout per approved plans.
OH Scope: The Fire Sprinkler scope consists of replacing 242 existing heads with new quick response heads. The fire sprinkler system work shall comply with the IFC 2006, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD08-00155. Reference FIR07-01005 for fees.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/1/20085/1/20085/1/2008PPASS
DetailsForrest France
Noted corrections are complete, fire sprinkler permit scope finaled.
INSP-Sprinkler Rough-in4/25/20084/25/20084/25/2008PFAIL
DetailsForrest France
Noted two overspaced heads on a branch line at the east open office area, three heads at one conference room do not meet spacing requirements off adjacent walls, see as-built plans for red-lined annotations. The remainder of overhead install per the permit scope is approved for cover.
INSP-Sprinkler Rough-in4/15/20084/15/20084/16/2008PFAIL
DetailsForrest France
Field installation does not match approved plan set, several conference rooms have four heads instead of two as shown on drawings, one storage room is overspaced, need to provide plans reflecting actual head layout prior to approval for cover at the drop ceilings.
Inspection Record Card- Fire4/14/2008 4/14/2008 DONE
DetailsPatricia Smith
PLANS/APPL TAKEN TO FRONT DESK  4/14/2008 DONE
Telephone call  4/14/2008 DONE
left vm for brodie at ###-#### - permit ready and fees given
Permit Ready to Issue  4/14/2008 DONE
Issue and Print Permit  4/14/2008 DONE
Sprinkler Plan Check3/27/2008 4/9/2008 PASS
Details
plans are approved
Application received  3/27/2008  
Pending Assignment by SAM3/27/2008