INSP-Final Inspection | 5/1/2008 | 5/1/2008 | 5/1/2008 | P | PASS |
Forrest France
|
|
|
Noted corrections are complete, fire sprinkler permit scope finaled.
|
INSP-Sprinkler Rough-in | 4/25/2008 | 4/25/2008 | 4/25/2008 | P | FAIL |
Forrest France
|
|
|
Noted two overspaced heads on a branch line at the east open office area, three heads at one conference room do not meet spacing requirements off adjacent walls, see as-built plans for red-lined annotations. The remainder of overhead install per the permit scope is approved for cover.
|
INSP-Sprinkler Rough-in | 4/15/2008 | 4/15/2008 | 4/16/2008 | P | FAIL |
Forrest France
|
|
|
Field installation does not match approved plan set, several conference rooms have four heads instead of two as shown on drawings, one storage room is overspaced, need to provide plans reflecting actual head layout prior to approval for cover at the drop ceilings.
|
Inspection Record Card- Fire | 4/14/2008 | | 4/14/2008 | | DONE |
Patricia Smith
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/14/2008 | | DONE |
|
|
|
|
Telephone call | | | 4/14/2008 | | DONE |
|
|
|
left vm for brodie at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 4/14/2008 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/14/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/27/2008 | | 4/9/2008 | | PASS |
|
|
|
plans are approved
|
Application received | | | 3/27/2008 | | |
|
|
|
|
Pending Assignment by SAM | 3/27/2008 | | | | |
|
|
|
|