Permit Information
Permit NumberFIR08-00243
StatusFinaled
Name CURTIS FIRESPRINKLER SERVICE INC
Site Address 4614 W STATE ST
Project NameCOLLISTER SHOPPING CTR
Customer Number 
ePlanReview 
Description
FIR Scope: OH - The Fire Sprinkler scope consists of adding an auxiliary anti-freeze system to serve the canopy only. The fire sprinkler system work shall comply with the IFC 2006, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD07-03079.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/8/20089/9/20089/9/2008PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection9/5/20089/5/20089/5/2008PFAIL
DetailsTroy Cobbley
Provide expansion tank for the anti-freeze loop, provide certification for the backflow, provide inspection tag and provide electric alarm bell.
INSP-Sprinkler Rough-in/Hydro7/9/20087/9/20087/9/2008APASS
DetailsTroy Cobbley
Overhead hydro test passed. Rough-in passed.
INSP-Sprinkler Rough-in/Hydro7/8/20087/8/20087/8/2008PFAIL
DetailsTroy Cobbley
The overhead hydro failed. No rough-in inspection performed.
Issue permit  5/9/2008  
Inspection Record Card- Fire5/8/2008 5/8/2008 DONE
DetailsPatricia Smith
PLANS/APPL TAKEN TO FRONT DESK  5/8/2008 DONE
Telephone call  5/8/2008 DONE
t/c w don curtis at ###-#### - permit ready and fees given
Permit Ready to Issue  5/8/2008 DONE
Sprinkler Plan Check4/2/2008 5/7/2008 PASS
Details
plans are approved
Case Summary  4/24/2008 DONE
Plan resubmittals received  4/24/2008  
received application and three copies of submittal packet and six copies of sheets FP1, FP2; taken to fire review
Sprinkler Plan Check4/2/2008 4/21/2008 FAIL
Details
These plans were denied for lack of or incorrect information. Upon request, the rejected set of plans and data may be retrieved from my office for salvage. The rejected set will be maintained for 5 working days.

Case Summary  4/2/2008 DONE
Application received  4/2/2008  
Pending Assignment by SAM4/2/2008