Permit Information
Permit NumberFIR08-00256
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 2758 S FEATHERLY WAY
Project NameSheffield Building #1
Customer Number 
ePlanReview 
Description
Bldg. Scope of Work:
(ADA COUNTY EMS - SHEFFIELD BUILDING #1) To build out and finish a 2,432 sq. ft. portion of an 7,800 sq. ft. building as an office, activity area, kitchen, three residential sleeping rooms, office and one emergency vehicle parking garage for Ada County Paramedics per approved plans and CUP07-00143.This BUILDING is to be fully sprinklered as a condition of this permit due to residential occupancy. Work includes construction of interior non-bearing walls to create the office, dining/living, kitchen, mechanical, bedrooms, laundry, restrooms, data and ambulance storage rooms. Plans indicate a 1-hour wall between this tenant space and space to east and between the ambulance storage and other use areas with door/frame/hardware assemblies of 60 minutes for doors 102A & 106. Work also includes new suspended ceiling grid system installed per CISCA guidelines in main areas and hard drywall lid in ambulance storage, restrooms, sleeping , mechanical and data rooms; upgrade electrical, mechanical & plumbing and install new NFPA 13 sprinkler with alarm system throughout the building as a condition of this permit due to 'R' occupancy sleeping rooms. All per approved plans including red-lined notes on plans and all attached plan review comments and conditions of all reviewing agencies for this project. drs


UG Scope:
Shilo’s scope will begin from the existing and section and section of 6” C900 located 16’ onto the property line by United Water. From there, run 25’-0” of 6” C900 out and rise up into the riser room of an existing 7,800-ft/2 bldg. The fire sprinkler underground work shall comply with NFPA 13-2007, NFPA 24-2007 the IFC-2006, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire “Inspection Card” are required to be on site as a condition of this work, to provide witness of compliance verification of minimum fire code. This permit is attached to building permit: BLD08-00277. The overhead will be submitted under a separate permit.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/7/20087/9/20087/10/2008PPASS
DetailsForrest France
Overhead and foward flush completed. See Forrest notes on FIR08-00256. KR
INSP-Supply line flush6/26/20086/26/20086/26/2008PPART
DetailsForrest France
UG fire supply line flush okayed
INSP-Sprinkler Rough-in/Hydro6/24/20086/25/20086/26/2008APART
DetailsForrest France
UG fire supply line hydrostatic testing completed.
INSP-Supply line flush6/24/20086/25/20086/25/2008ANR
DetailsForrest France
Need to coordinate inspection with United Water Co. as discussed.
INSP-Sprinkler Rough-in5/8/20085/9/20085/9/2008APASS
DetailsTroy Cobbley
The underground supply line was installed as per plan and can be covered. It took three trips to perfom this inspection due to the piping being covered with sand and no access into the trench to verify the pipe size installed.
Issue and Print Permit  4/30/2008  
Plan assigned to (SAM)4/9/2008 4/29/2008 PASS
DetailsCathy Brown
4/29/2008 16:13:57 CMB - activity updated through activity FIRA22 from case FIR08-00256.
PLANS/APPL TAKEN TO FRONT DESK  4/29/2008 DONE
Inspection Record Card- Fire4/29/2008 4/29/2008 DONE
DetailsCathy Brown
Telephone call  4/29/2008 DONE
tlk to Lillie ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  4/29/2008 DONE
Sprinkler Plan Check4/9/2008 4/26/2008 PASS
Details
Plans are approved by Bryan Johnson
Application received  4/9/2008  
Pending Assignment by SAM4/9/2008