Miscellaneous action | | | 5/13/2010 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 4/14/2009 | 4/15/2009 | 4/15/2009 | A | PASS |
Troy Cobbley
|
|
|
The sign at the FDC has been provided. Permit is finaled.
|
INSP-Final Inspection | 4/2/2009 | 4/3/2009 | 4/3/2009 | A | FAIL |
Troy Cobbley
|
|
|
The valves have been locked open but a sign mounted above the FDC stating the required gpm and psi was not provided. I spoke to chris with debest about the sign.
|
INSP-Sprinkler Rough-in/Hydro | 3/30/2009 | 3/31/2009 | 3/31/2009 | A | PART |
Forrest France
|
|
|
AG hydrostatic testing completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 3/20/2009 | 3/20/2009 | 3/20/2009 | P | FAIL |
Forrest France
|
|
|
Hydrostatic testing failed due to visible leakage at hose valve connections and pressure loss at the guages.
|
INSP-Sprinkler Rough-in/Hydro | 3/19/2009 | 3/20/2009 | 3/20/2009 | A | PART |
Forrest France
|
|
|
Flow testing at remote hose stations per system design completed satisfactory in conjunction with fire dept. apparatus at the street side FDC.
|
INSP-Sprinkler Rough-in/Hydro | 1/14/2009 | 1/14/2009 | 1/14/2009 | A | PART |
Forrest France
|
|
|
Rough-in passed
|
INSP-Sprinkler Rough-in/Hydro | 1/8/2009 | 1/9/2009 | 1/13/2009 | A | PART |
Forrest France
|
|
|
See inspection comments 1/13.
|
INSP-Sprinkler Rough-in/Hydro | 1/13/2009 | 1/13/2009 | 1/13/2009 | A | PART |
Forrest France
|
|
|
Rough-in inspection completed satisfactory, discussed acceptance testing, hydrostatic and pneumatic testing schedule, and remainder of items needed prior to final including signage, locks at control valves, review notes, etc.
|
INSP-Conference | 1/8/2009 | 1/8/2009 | 1/8/2009 | P | DONE |
Forrest France
|
|
|
Regarding FDC valves at the standpipes.
|
FIR-Aging Inspection | 8/6/2008 | 8/6/2008 | 8/6/2008 | | DEFR |
Forrest France
|
|
|
Site construction underway.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/6/2008 | | DONE |
Cathy Brown
|
|
|
|
Inspection Record Card- Fire | 5/6/2008 | | 5/6/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 5/6/2008 | | DONE |
Cathy Brown
|
|
|
lft ms with receptionist for gerald ebeling ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 5/6/2008 | | DONE |
Cathy Brown
|
|
|
|
Issue and Print Permit | | | 5/6/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 4/15/2008 | | 5/4/2008 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Application received | | | 4/15/2008 | | |
|
|
|
|
Pending Assignment by SAM | 4/15/2008 | | | | |
|
|
|
|