INSP-Final Inspection | 7/1/2008 | 7/1/2008 | 7/1/2008 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in | 6/19/2008 | 6/19/2008 | 6/19/2008 | P | PASS |
Troy Cobbley
|
|
|
The tenting appears to be satifactory. I had Lonnie modify tenting in one location. Blow-in insulation can be installed.
|
INSP-Sprinkler Rough-in | 5/29/2008 | 5/30/2008 | 5/30/2008 | A | PART |
Troy Cobbley
|
|
|
the underground flush passed. There is sprinkler blockage in the mater bathroom at the tub/shower enclosure and cpvc piping is exposed at the riser. A tenting inspection will be required as well as an inspection to see the insulation.
|
Issue and Print Permit | | | 5/28/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/27/2008 | | DONE |
Cathy Brown
|
|
|
|
Inspection Record Card- Fire | 5/27/2008 | | 5/27/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 5/27/2008 | | DONE |
Cathy Brown
|
|
|
tlk to jonn edes ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 5/27/2008 | | DONE |
Cathy Brown
|
|
|
|
Sprinkler Plan Check | 5/12/2008 | | 5/21/2008 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Plan resubmittals received | | | 5/12/2008 | | |
|
|
|
Received five copies of application, product data and sheet FP-1; taken to fire review
|
Sprinkler Plan Check | 4/22/2008 | | 5/9/2008 | | FAIL |
|
|
|
These plans were denied based on flaws in the calculations. Upon request, the denied set may be retrieved from my office for salvage. The denied set will be maintained for 5 working days.
|
Application received | | | 4/22/2008 | | |
|
|
|
|
Pending Assignment by SAM | 4/22/2008 | | | | |
|
|
|
|