INSP-Final Inspection | 6/30/2008 | 7/1/2008 | 7/1/2008 | A | PASS |
Forrest France
|
|
|
Fire sprinkler hydro completed also final inspection. KR
|
INSP-Final Inspection | 6/27/2008 | 6/30/2008 | 6/30/2008 | A | NR |
Forrest France
|
|
|
Reschedule for tomorrow, with fire alarm inspection. KR
|
INSP-Sprinkler Rough-in | 6/25/2008 | 6/26/2008 | 6/26/2008 | A | DONE |
Forrest France
|
|
|
Rough-in inspecction complete. Minor changes, will provide as-builts before final. KR
|
Issue and Print Permit | | | 6/16/2008 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 4/25/2008 | | 6/13/2008 | | PASS |
Cathy Brown
|
|
|
6/13/2008 14:44:20 CMB - activity updated through activity FIRA22 from case FIR08-00300.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/13/2008 | | DONE |
Cathy Brown
|
|
|
|
Inspection Record Card- Fire | 6/13/2008 | | 6/13/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 6/13/2008 | | DONE |
Cathy Brown
|
|
|
tlk to curtis johnson ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 6/13/2008 | | DONE |
Cathy Brown
|
|
|
|
Sprinkler Plan Check | 5/29/2008 | | 6/12/2008 | | PASS |
|
|
|
Plans & Calculations are Approved by Bryan Johnson
|
Plan resubmittals received | | | 5/29/2008 | | |
|
|
|
Received application, hydraulic calcs, product data and four copies of FP-01; taken to fire review
|
Plan resubmittals received | | | 5/7/2008 | | |
|
|
|
Received application and six copies of hydraulic calcs and product data and sheet FP-01; taken to fire review
|
Sprinkler Plan Check | 4/25/2008 | | 4/26/2008 | | FAIL |
|
|
|
These plans were denied due to calculation flaws. Upon request, the denied set may be retrieved from my office for salvage.
|
Application received | | | 4/25/2008 | | |
|
|
|
|
Pending Assignment by SAM | 4/25/2008 | | | | |
|
|
|
|