Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR08-00322
StatusFinaled
Name COMMERCIAL FIRE PROTECTION
Site Address 300 N MILWAUKEE ST
Project NameJC PENNY
Customer Number 
ePlanReview 
Description
FIR Work Scope: The Fire Sprinkler scope consists of adding and relocating 27 heads to accommodate a new wall & ceiling lay out. The fire sprinkler system work shall comply with the IFC 2006, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD08-00434.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/16/20089/16/20089/17/2008PPASS
DetailsTroy Cobbley
permit finaled
INSP-Sprinkler Rough-in/Hydro8/25/20088/26/20088/26/2008APASS
DetailsTroy Cobbley
Permit finaled.
INSP-Sprinkler Rough-in/Hydro7/28/20087/28/20087/28/2008PFAIL
DetailsTroy Cobbley
Per Vance the approved plans are missing. Terry is going to get replacement plans and the inspection will be called back in. No inspection was performed.
Issue and Print Permit  5/15/2008 DONE
Inspection Record Card- Fire5/12/2008 5/12/2008 DONE
DetailsPatricia Smith
PLANS/APPL TAKEN TO FRONT DESK  5/12/2008 DONE
Telephone call  5/12/2008 DONE
t/c w john warnick at ###-#### - permit ready and fees given
Permit Ready to Issue  5/12/2008 DONE
Sprinkler Plan Check5/6/2008 5/8/2008 PASS
Details
plans are approved
Case Summary  5/6/2008 DONE
Application received  5/6/2008  
Pending Assignment by SAM5/6/2008