INSP-Final Inspection | 12/9/2008 | 12/10/2008 | 12/10/2008 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit work finaled, noted corrections verified for completion.
|
INSP-Final Inspection | 11/5/2008 | 11/6/2008 | 11/6/2008 | A | FAIL |
Forrest France
|
|
|
See locations marked on cleanroom plan copies for areas in need of adjustment due to heads obstructed by adjacent equipment and supports at the ceilings.
|
INSP-Final Inspection | 10/31/2008 | 11/5/2008 | 11/5/2008 | A | DEFR |
Forrest France
|
|
|
Phone #: ###-#### Internet Inspection Request from: Wayne Berry
|
Issue and Print Permit | | | 8/21/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/20/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | | | 7/30/2008 | | PASS |
|
|
|
On site review and approval of revised plans done by T. Cobbley.
|
Meeting | | | 7/2/2008 | | DONE |
|
|
|
Site review of new OH material handling conveyors which create a sprinkler obstruction situation, with Paul Marcolina and Steve Murdock. Depth and extent of OH conveyor equipment preclude meeting the NFPA 13, 8.5.5 Obstruction to Sprinkler Discharge spacing requirements. They propose using the Obstructed Construction requirements, but the nature of the obstructions does not fit the Construction Obstruction definitions of 3.7. They agreed to investigate out how their other facility protected similar conveyor obstructions, obtain FM's insurance recommendations, and look into the possibility of installing baffles to simulate construction obstructions as defined by NFPA 13, 3.7 so as to allow use of those requirements. SLR
|
Sprinkler Plan Check | | | 6/19/2008 | | FAIL |
|
|
|
Initial plan review failed - does not meet spacing requirements of NFPA 13 for Obstructions. Referred to S. Rogers.
|
Plan assigned to (Scott) | | | 5/8/2008 | | DONE |
Sam Rogers
|
|
|
This permit was created on the web by Paul Marcolina
|
Plan assigned to (SAM) | | | 5/8/2008 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|