INSP-Final Inspection | 6/4/2008 | 6/4/2008 | 6/4/2008 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 6/4/2008 | 6/4/2008 | 6/4/2008 | P | NR |
Forrest France
|
|
|
Pending request for building permit final fire life safety inspection-will complete sprinkler final in conjunction per discussion with general contractor.
|
INSP-Final Inspection | 6/2/2008 | 6/3/2008 | 6/3/2008 | A | FAIL |
Forrest France
|
|
|
Project is not ready for final at this time due to finishes and construction underway-missng escutcheons, paint masking, etc.
|
INSP-Sprinkler Rough-in | 5/22/2008 | 5/22/2008 | 5/22/2008 | P | PART |
Forrest France
|
|
|
Approved for ceiling cover as noted, existing system riser is current with an annual inspection.
|
INSP-Sprinkler Rough-in | 5/20/2008 | 5/21/2008 | 5/21/2008 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler modifications are okay for ceiling cover at the remodel area.
|
Sprinkler Plan Check | 5/20/2008 | | 5/20/2008 | | PASS |
Scott Arellano
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/20/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/20/2008 | | 5/20/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 5/20/2008 | | DONE |
Cathy Brown
|
|
|
tlk to jeff ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 5/20/2008 | | DONE |
Cathy Brown
|
|
|
|
Issue and Print Permit | | | 5/20/2008 | | DONE |
|
|
|
|
Application received | | | 5/15/2008 | | |
|
|
|
|
Pending Assignment by SAM | 5/15/2008 | | | | |
|
|
|
|