INSP-Final Inspection | 10/15/2008 | 10/15/2008 | 10/15/2008 | P | PASS |
Troy Cobbley
|
|
|
All corrections made per last inspection. KR
|
INSP-Final Inspection | 10/13/2008 | 10/14/2008 | 10/14/2008 | P | FAIL |
Troy Cobbley
|
|
|
bryan Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 10/13/2008 | 10/14/2008 | 10/14/2008 | P | FAIL |
Troy Cobbley
|
|
|
Need the ball drip installed at the yard valves and the couplings coated with zinc.
|
INSP-Sprinkler Rough-in | 10/6/2008 | 10/6/2008 | 10/6/2008 | P | PASS |
Troy Cobbley
|
|
|
The remaining underground piping can be covered
|
CHANGE STATUS TO (ISS) | | | 10/6/2008 | | |
|
|
|
no charge for permit
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/3/2008 | | |
|
|
|
|
Inspection Record Card- Fire | 10/3/2008 | | 10/3/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 10/3/2008 | | DONE |
Cathy Brown
|
|
|
tlk to jeff anderson ###-#### that permit and no charge for permti to be picked up
|
Permit Ready to Issue | | | 10/3/2008 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/2/2008 | | DONE |
Scott Arellano
|
|
|
AS Built shop drawings for the FDC and Yard hydrant approved.
|
Plan resubmittals received | | | 9/10/2008 | | |
Sam Rogers
|
|
|
Plan modification submitted
|
INSP-Sprinkler Rough-in | 7/7/2008 | 7/7/2008 | 7/7/2008 | P | PART |
Troy Cobbley
|
|
|
The supply piping for the underground has been installed differently from the approved plans. Its connection point to united water has been moved approximately 8' to the north which required two 45 elbows to be installed. This section of underground piping is ok to cover to the fence. The changes have been noted on the plans, signed and dated. Also the 4" stub-out for the FDC has been installed and is marked on the plans as well. This 5' stub-out has been installed per plan.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/11/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/11/2008 | | 6/11/2008 | | DONE |
Cathy Brown
|
|
|
|
Issue and Print Permit | | | 6/11/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/19/2008 | | 6/10/2008 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Sprinkler Plan Check | 5/19/2008 | | 5/28/2008 | | FAIL |
|
|
|
These plans were denied due to non compliance issues. Upon request the denied set of plans may be retrieved from my office for salvage.
|
Plan resubmittals received | | | 5/27/2008 | | |
|
|
|
Received five copies of application and sheet FP1 of 2; taken to fire review
|
Application received | | | 5/19/2008 | | |
|
|
|
|
Pending Assignment by SAM | 5/19/2008 | | 5/19/2008 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 9/10/2008 | | | | |
Sam Rogers
|
|
|
Plan modification submitted 9-9-08
|