Miscellaneous action | | | 10/26/2009 | | DONE |
|
|
|
Fire alarm plans taken to records
|
INSP-Final Inspection | 10/9/2009 | 10/9/2009 | 10/9/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 10/7/2009 | 10/8/2009 | 10/8/2009 | P | FAIL |
Troy Cobbley
|
|
|
All deficiencies on the 2nd floor have been corrected. The 1st floor deficiencies are not complete.
|
INSP-Sprinkler Rough-in/Hydro | 9/10/2009 | 9/11/2009 | 9/11/2009 | A | PASS |
Troy Cobbley
|
|
|
The fire alarm is passed in the first floor shower room and isolation room.
|
INSP-Alarm Testing | 9/10/2009 | 9/10/2009 | 9/10/2009 | P | FAIL |
Troy Cobbley
|
|
|
The fire alarm contractor was not available while I was on site for the inspection. To be rescheduled.
|
INSP-Alarm Testing | 6/30/2009 | 6/30/2009 | 6/30/2009 | P | PASS |
Troy Cobbley
|
|
|
The door release for the Skilled Nursing Area B doors has been installed and tested. Also the fire alarm has been tested in the new shower room, second floor, of Skilled Nursing. See the city approved plans for location of rooms.
|
INSP-Alarm Testing | 6/29/2009 | 6/29/2009 | 6/29/2009 | P | FAIL |
Troy Cobbley
|
|
|
All items tested okay except door release for delayed egress locks to be installed at nurse's station as discussed. Provide weatherproof cover on a/v device in bathroom with shower as discussed. Provide as-builts reflecting changes as discussed.
|
Inspection Record Card- Fire | 6/19/2009 | | 6/19/2009 | | DONE |
|
|
|
|
Telephone call | | | 6/19/2009 | | DONE |
|
|
|
t/c w robert gobler at ###-#### - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 6/19/2009 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/19/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
(F) Reprint permit | | | 6/19/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Alarm Plan Check | 6/18/2009 | | 6/18/2009 | | PASS |
Stephanie L. Cobbley
|
|
|
See redlines and review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 6/18/2009 | | DONE |
|
|
|
Approved redlined plans available at front counter
|
Plan assigned to (Stephanie) | 6/17/2009 | | 6/18/2009 | | DONE |
Stephanie L. Cobbley
|
|
|
6/18/2009 14:10:34 SLC - activity updated through activity FIRA24 from case FIR08-00382.
|
(F) Reprint permit | | | 6/17/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Case Summary | | | 6/17/2009 | | |
Alexandra L. DeYoung
|
|
|
|
Plan resubmittals received | | | 6/17/2009 | | |
Stacey Carlson
|
|
|
Rec'd plan mod- two copies of plans- taken to Stephanie
|
INSP-Alarm Testing | 6/11/2009 | 6/11/2009 | 6/12/2009 | P | FAIL |
Troy Cobbley
|
|
|
Area in question is at the main entry lobby. Smoke detectors for door holder shutdown have been relocated from original installation and are not part of the submitted scope of work. No inspection performed. Spoke to contractor about what would be required for submitting the non-scope changed area. Also discussed requirement for submitting a plan modification for changes within the scope of work but are too extensive for field approval.
|
Override - Parcel Holds | 6/11/2009 | 1/1/1900 | 6/11/2009 | | |
|
|
|
test only
|
INSP-Alarm Testing | 6/5/2009 | 6/5/2009 | 6/5/2009 | P | PART |
Troy Cobbley
|
|
|
See the as-builts signed by me with todays date for the locations where the fire alarm system tested ok.
|
Override - Parcel Holds | 6/5/2009 | 1/1/1900 | 6/5/2009 | | |
|
|
|
not in aaffected area
|
INSP-Alarm Testing | 6/3/2009 | 6/3/2009 | 6/3/2009 | P | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for deficiancies. They include smoke detector and a door holder that are not shown on the plans. A door holder that is shown on the plans but has not been installed. A remote annunciator that has not been installed. A smoke detector that does not set off the general alarm. A room missing a strobe. A wall mount a/v has been revised to a ceiling mount and was the wrong candella. All of these items are in a very small area.
|
Override - Parcel Holds | 6/3/2009 | 1/1/1900 | 6/3/2009 | | |
|
|
|
fire alarm testing
|
INSP-Alarm Testing | 2/25/2009 | 2/25/2009 | 2/25/2009 | A | PART |
Troy Cobbley
|
|
|
Duplicate inspection see todays entry for items addressed
|
INSP-Final Inspection | 2/24/2009 | 2/25/2009 | 2/25/2009 | A | PART |
Troy Cobbley
|
|
|
The fire alarm systems in the first and second floor dining areas operated correctly. As-built plans will be required at a minimum or possibly resubmittals depending on how many other changes are made to the project. Just in these two areas the a/v's are ceiling mount instead of wall mount, duct smoke detectors have been added, spot type detector has been added for hvac shutdown and the wall layout has changed. Also the spot type detector being used for hvac shut down has been installed out side of its listing as far as max. cfm and the physical positioning within the duct opening.
|
INSP-Final Inspection | 2/23/2009 | 2/24/2009 | 2/24/2009 | P | FAIL |
Troy Cobbley
|
|
|
Apparently the city approved plans have been lost. No inspection was performed.
|
FIR-Aging Inspection | 11/17/2008 | 11/17/2008 | 11/17/2008 | | DONE |
Forrest France
|
|
|
Work in progress, construction underway.
|
Inspection Record Card- Fire | 8/15/2008 | | 8/15/2008 | | DONE |
|
|
|
|
Telephone call | | | 8/15/2008 | | DONE |
|
|
|
left vm for robert gobler at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 8/15/2008 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/15/2008 | | DONE |
|
|
|
|
Alarm Plan Check | | | 8/14/2008 | | PASS |
|
|
|
See redlines and review comments
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/14/2008 | | DONE |
|
|
|
|
Plan resubmittals received | | | 8/8/2008 | | |
Stephanie L. Cobbley
|
|
|
Received application two binders of submittal inforamation, and two copies of demo plan sheets FA0, FAD2.1.1, FAD2.1.2, FAD2.2.1, FAD2.2.2; two copies of fire alarm plan sheets FAD2.1.1, FAD2.1.2, FAD2.2.1, FAD2.2.2, FA3.1, FA3.2, FA3.3, FA3.4; taken to Fire Review
|
Plan assigned to (Stephanie) | 8/8/2008 | | 8/8/2008 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Alarm Plan Check | | | 6/6/2008 | | FAIL |
|
|
|
See redlined drawings and review comments
|
Miscellaneous action | | | 6/6/2008 | | DONE |
|
|
|
Faxed review comments to Robert Gobler
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/6/2008 | | DONE |
|
|
|
Redlined plans and review comments ready for pick up
|
Application received | | | 5/30/2008 | | |
|
|
|
|
Plan assigned to (Stephanie) | 5/30/2008 | | 5/30/2008 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Case Summary | | | 5/30/2008 | | DONE |
|
|
|
|