INSP-Final Inspection | 10/16/2008 | 10/17/2008 | 10/17/2008 | A | PASS |
Forrest France
|
|
|
Correction notice items verified for completion, fire sprinkler permit finaled.
|
INSP-Final Inspection | 10/13/2008 | 10/14/2008 | 10/14/2008 | A | FAIL |
Forrest France
|
|
|
Inspection failed due to several items including one painted head at the electrical room, leaking pendent at the pharmacy area, dry pendent heads are not yet installed at the coolers, missing escutcheon at the staff restroom, provide correct pipe hanger at the outside storage locker, need as-builts for field mods, PIV tamper is not correcly adjusted, waterflow switch needs adjustment, provide pitot guage for forward flow testing, need main control signage at the riser #1 and #2 shutoff valves.
|
INSP-Sprinkler Rough-in/Hydro | 9/18/2008 | 9/19/2008 | 9/19/2008 | A | PART |
Forrest France
|
|
|
OH hydrostatic testing including the wet and antifreeze loop system passed, verified c/n items, noted concealed heads at the restrooms may be obstructed by adjacent surface mounted light fixtures when installed.
|
INSP-Sprinkler Rough-in | 8/22/2008 | 8/25/2008 | 8/25/2008 | A | FAIL |
Forrest France
|
|
|
SW heads at the sign tower antifreeze loop are overspaced and below max. listed distance from the ceiling, noted several missing retaining straps at numerous locations including mains and branch lines-somel installed while on site, combustibles above the restrooms must be removed or protection provided, waiting area drops are 3/4"-plan shows 1/2" heads, four upright heads at the stock room are obstructed by beams or exceed min. spacing.
|
Issue and Print Permit | | | 8/7/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/24/2008 | | 8/4/2008 | | PASS |
|
|
|
This was the third review of these plans. Plans are approved by Bryan Johnson
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/4/2008 | | DONE |
Cathy Brown
|
|
|
|
Inspection Record Card- Fire | 8/4/2008 | | 8/4/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 8/4/2008 | | DONE |
Cathy Brown
|
|
|
tlk to lillie ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 8/4/2008 | | DONE |
Cathy Brown
|
|
|
|
Early Start | | | 8/1/2008 | | DONE |
|
|
|
Early Start request approved. Plans have failed review twice, the agreement specifies contractor responsible for any modificications necessary after plans are approved. doc attached.
|
Plan resubmittals received | | | 7/24/2008 | | |
Sam Rogers
|
|
|
|
Sprinkler Plan Check | 7/10/2008 | | 7/15/2008 | | FAIL |
|
|
|
These plans were denied due to missing or inaccurate information. Upon request, the denied set of plans may be retrieved from my office for salvage. The denied set of plans will be maintained for 5 working days.
|
Plan resubmittals received | | | 7/10/2008 | | |
Scott Arellano
|
|
|
received fire spr app. & "5" sets of plans- put plans on fire shelf
|
Sprinkler Plan Check | 6/4/2008 | | 6/20/2008 | | FAIL |
|
|
|
These plans were denied due to lacking or incorrect information. Upon request the denied set of plans may be retrieved from my office for salvage. The denied set will be maintained for 5 working days.
|
Application received | | | 6/4/2008 | | |
|
|
|
|
Pending Assignment by SAM | 6/4/2008 | | | | |
|
|
|
|
Plan assigned to (SAM) | 6/4/2008 | | | | |
|
|
|
|