Miscellaneous action | | | 3/10/2009 | | DONE |
|
|
|
Sent for archiving
|
INSP-Final Inspection | 1/28/2009 | 1/28/2009 | 1/28/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Supply line flush | 9/11/2008 | 9/12/2008 | 9/12/2008 | P | PASS |
Troy Cobbley
|
|
|
The underground flush passed
|
INSP-Sprinkler Rough-in/Hydro | 9/10/2008 | 9/11/2008 | 9/11/2008 | P | PASS |
Troy Cobbley
|
|
|
The underground hydro test passed
|
INSP-Sprinkler Rough-in | 7/3/2008 | 7/3/2008 | 7/3/2008 | P | PART |
Forrest France
|
|
|
UG fire supply line installation is approved for cover.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/27/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 6/27/2008 | | DONE |
Cathy Brown
|
|
|
tlk to lilly ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 6/27/2008 | | DONE |
Cathy Brown
|
|
|
|
Issue and Print Permit | | | 6/27/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/11/2008 | | 6/23/2008 | | |
|
|
|
|
Sprinkler Plan Check | 6/11/2008 | | 6/23/2008 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Case Summary | | | 6/11/2008 | | DONE |
|
|
|
|
Application received | | | 6/11/2008 | | |
|
|
|
|
Pending Assignment by SAM | 6/11/2008 | | | | |
|
|
|
|