INSP-Final Inspection | 10/21/2008 | 10/22/2008 | 10/22/2008 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 9/26/2008 | 9/29/2008 | 9/29/2008 | P | FAIL |
Troy Cobbley
|
|
|
Need the tamper switches installed and the interconnect with the fire alarm system tested.
|
INSP-Sprinkler Rough-in | 7/29/2008 | 7/29/2008 | 7/29/2008 | P | PASS |
Troy Cobbley
|
|
|
The tenting appears to be adequate.
|
INSP-Sprinkler Rough-in/Hydro | 7/8/2008 | 7/10/2008 | 7/10/2008 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping rough-in passed. Will need a follow-up inspection for the tenting and insulation. The riser has not been built yet.
|
INSP-Sprinkler Rough-in/Hydro | 7/8/2008 | 7/9/2008 | 7/8/2008 | A | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 7/8/2008 at 4:17:50 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Jul 8 2008 4:20PM.
|
Issue and Print Permit | | | 7/8/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/2/2008 | | DONE |
Cathy Brown
|
|
|
|
Inspection Record Card- Fire | 7/2/2008 | | 7/2/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 7/2/2008 | | DONE |
Cathy Brown
|
|
|
tlk to jim dane ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 7/2/2008 | | DONE |
Cathy Brown
|
|
|
|
Sprinkler Plan Check | 6/11/2008 | | 6/26/2008 | | PASS |
|
|
|
Plans & Calculations Are Approved by Bryan Johnson
|
Application received | | | 6/11/2008 | | |
|
|
|
|
Case Summary | | | 6/11/2008 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 6/11/2008 | | | | |
|
|
|
|
Pending Assignment by SAM | 6/11/2008 | | | | |
|
|
|
|