Miscellaneous action | | | 5/13/2010 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 7/13/2009 | 7/14/2009 | 7/14/2009 | A | PASS |
Troy Cobbley
|
|
|
Pemit finaled as per TIm Frost
|
INSP-Final Inspection | 7/9/2009 | 7/10/2009 | 7/10/2009 | A | FAIL |
Forrest France
|
|
|
Correction notice item from the previous inspection done 6/18 is not finished. Pendent head at the master closet obstructed by an adjacent light fixture.
|
INSP-Sprinkler Rough-in/Hydro | 6/17/2009 | 6/18/2009 | 6/18/2009 | A | FAIL |
Forrest France
|
|
|
Noted one obstructed head at the master closet by an adjacent surface mounted light fixture, tape and paper at two pendents removed while on site, remainder of work is acceptable.
|
FIR-Aging Inspection | 10/10/2008 | 10/10/2008 | 10/13/2008 | | DONE |
Forrest France
|
|
|
Work in progress, construction underway.
|
Issue and Print Permit | | | 7/8/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/7/2008 | | DONE |
Cathy Brown
|
|
|
|
Permit Ready to Issue | | | 7/7/2008 | | DONE |
Cathy Brown
|
|
|
|
Inspection Record Card- Fire | 6/20/2008 | | 7/7/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/20/2008 | | 6/30/2008 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Application received | | | 6/20/2008 | | |
|
|
|
|
Pending Assignment by SAM | 6/20/2008 | | | | |
Sam Rogers
|
|
|
|