Permit NumberFIR08-00452
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1010 W WASHINGTON ST
Project NameBoise High School
Customer Number 
ePlanReview 
Description
FIR Work Scope: The Fire Sprinkler scope consists of adding 9 down head on the Basement Level to accommodate a new wall lay out in the Computer / Lab Room 051. No calculation were required as the modification does not appear to adversely affect the operation of the system The fire sprinkler system work shall comply with the IFC 2006, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD08-00956 and Quick Permits FIR08-00417 & FIR08-00416.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/14/20088/15/20088/15/2008PPASS
DetailsForrest France
Fire sprinkler permit finaled.
INSP-Final Inspection8/13/20088/14/20088/14/2008PNR
DetailsForrest France
Final pending as-built plans for heads relocated in the corridor and tile/escutcheons at all areas.
INSP-Sprinkler Rough-in8/7/20088/8/20088/8/2008APART
DetailsForrest France
2nd floor overhead work at the classrooms is approved for cover, noted modifications at the corridor to be indicated on as-built plans per discussion with the designer, basement area is missing five escutcheons at pendent heads.
INSP-Sprinkler Rough-in8/5/20088/6/20088/6/2008ANH
DetailsForrest France
This is rough to cover for the 2nd fl. Plans are on site. Brian D is the contact. Thanks Phone #: ###-#### Internet Inspection Request from: Stan Beus ****NOTE: Wrong permit number request, this permit is for basement work in the adjacent building.
INSP-Sprinkler Rough-in7/28/20087/29/20087/29/2008APART
DetailsForrest France
Reinspection for the basement level computer lab room passed rough-in, okay for cover at the drop ceilings.
INSP-Sprinkler Rough-in7/21/20087/22/20087/22/2008AFAIL
DetailsForrest France
Field installation does not match approved plans including layout at the east side rooms, added head due to ceiling height change at the west side, contractor has installed 3/4 pendent heads despite approved drawings indicating 1/2 to be used, also lacking coverage for exposed combustible construction above the drop ceiling, corner adjacent to the south exit door is unprotected, provide accurate drawings prior to next inspection, ceiling cover is not approved at this time.
Inspection Record Card- Fire7/10/2008 7/10/2008 DONE
Details
PLANS/APPL TAKEN TO FRONT DESK  7/10/2008 DONE
Details
Telephone call  7/10/2008 DONE
Details
t/c w lily at ###-#### - permit ready and fees given
Permit Ready to Issue  7/10/2008 DONE
Details
Issue and Print Permit  7/10/2008 DONE
Sprinkler Plan Check6/24/2008 7/7/2008 PASS
Details
plans are approved
Application received  6/24/2008  
DetailsMarsha Smylie
Case Summary  6/24/2008  
DetailsMarsha Smylie
Pending Assignment by SAM6/24/2008    
DetailsSam Rogers