Miscellaneous action | | | 5/13/2010 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 4/28/2009 | 4/28/2009 | 4/28/2009 | P | PASS |
Forrest France
|
|
|
Shell sprinkler work okayed for final.
|
INSP-Sprinkler Rough-in/Hydro | 4/28/2009 | 4/28/2009 | 4/28/2009 | P | PART |
Forrest France
|
|
|
See activities under project related FIR08-00018 for the majority of inspections completed including the same scope of work for this permit.
|
Pending Assignment by SAM | 6/30/2008 | | 3/19/2009 | | DONE |
Tisha Gallop
|
|
|
3/19/2009 14:29:16 LEG - activity updated through activity FIRA158 from case FIR08-00018.
|
INSP-Sprinkler Rough-in/Hydro | 1/23/2009 | 1/27/2009 | 1/27/2009 | A | PART |
Forrest France
|
|
|
OH sprinkler piping and drops okayed for ceiling cover at the 7th floor common corridor, noted one missing hanger at an armover to be installed today, discussed sw head locations at the cable closets adjacent to the elevator hoistway.
|
INSP-Sprinkler Rough-in/Hydro | 1/22/2009 | 1/23/2009 | 1/23/2009 | A | PART |
Forrest France
|
|
|
6th floor common corridor overhead install okayed for cover.
|
INSP-Sprinkler Rough-in | 7/28/2008 | 7/30/2008 | 7/30/2008 | A | FAIL |
Forrest France
|
|
|
Inspection for overhead fire sprinkler rough-in at the 7th floor failed due to changes in floorplan, piping layout, number, type and location of heads at several areas. Differences between field installation and approved plans are beyond what can normally be accepted on "as-built" drawings, will need to provide approved resubmittal plans including all changes. The installation appears acceptable, however documentation must be provided.
|
Override - Parcel Holds | 7/28/2008 | 1/1/1900 | 7/28/2008 | | |
|
|
|
7th floor rough in
|
INSP-Sprinkler Rough-in/Hydro | 7/11/2008 | 7/14/2008 | 7/14/2008 | A | DEFR |
Troy Cobbley
|
|
|
Jeff and I agreed to have Forrest continue the inspections on this project due to agreements on sidewall head placement at the air conditioning units.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/10/2008 | | DONE |
Cathy Brown
|
|
|
|
Override - Parcel Holds | | | 7/10/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 7/10/2008 | | |
|
|
|
|
Permit Ready to Issue | | | 7/10/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 7/10/2008 | | DONE |
Cathy Brown
|
|
|
tlk to gerald ebeling ###-#### that permit and fees are ready to be picked up
|
Override - Parcel Holds | | | 7/10/2008 | | |
|
|
|
|
Issue and Print Permit | | | 7/10/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/30/2008 | | 7/8/2008 | | DONE |
Cathy Brown
|
|
|
|
Sprinkler Plan Check | 6/30/2008 | | 7/8/2008 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Application received | | | 6/30/2008 | | |
|
|
|
|