Miscellaneous action | | | 5/13/2010 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 3/30/2009 | 3/30/2009 | 3/30/2009 | A | PASS |
Forrest France
|
|
|
Items on correction notice have been completed, final fire sprinkler inspection passed.
|
INSP-Conference | 3/27/2009 | 3/27/2009 | 3/27/2009 | P | DONE |
Forrest France
|
|
|
Regarding unfinished basement area ceilings.
|
INSP-Final Inspection | 3/25/2009 | 3/26/2009 | 3/27/2009 | A | FAIL |
Forrest France
|
|
|
Noted two locations where sprinkler heads are blocked by adjacent light fixtures including the studio storage room 1st floor and a basement closet, missing sheetrock ceilings at basement rooms south side. Flow testing completed.
|
INSP-Supply line flush | 3/26/2009 | 3/26/2009 | 3/26/2009 | A | PART |
Forrest France
|
|
|
Supply line flush completed per activity notes 8/12.
|
INSP-Sprinkler Rough-in | 8/21/2008 | 8/22/2008 | 8/22/2008 | A | PART |
Forrest France
|
|
|
Plan resubmittals accepted regarding field modifications, tenting appears acceptable, noted corrections verified, overhead install is okay for cover.
|
Issue and Print Permit | | | 8/21/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/20/2008 | | DONE |
|
|
|
|
Telephone call | | | 8/20/2008 | | DONE |
|
|
|
t/c w jon edes at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 8/20/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/20/2008 | | 8/20/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/13/2008 | | 8/19/2008 | | PASS |
|
|
|
plans are approved
|
Plan resubmittals received | | | 8/13/2008 | | |
|
|
|
Plan Modification: Received three copies of application and sheets FP-1, FP-2; taken to fire review
|
INSP-Sprinkler Rough-in/Hydro | 8/11/2008 | 8/12/2008 | 8/12/2008 | A | FAIL |
Forrest France
|
|
|
Overhead rough-in is not approved for cover at this time due to field changes in pipe routing/sizes, 6 added heads, one deleted head, an added kitchen storage room in an upper level including 2 heads not shown on drawings, relocated heads etc. Plans will need to be resubmitted for approval matching the field installation prior to okay for cover. Noted possible obstructions by soffits at three rooms in the basement which need to comply with NFPA 13D 8.2.5.4.3, head at the riser room needs relocated as discussed for exposed CPVC riser install, be aware of possible light fixture obstructions. UG supply flush completed okay.
|
Issue and Print Permit | | | 7/24/2008 | | DONE |
|
|
|
|
Telephone call | | | 7/23/2008 | | DONE |
|
|
|
left vm for jon edes at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 7/23/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/8/2008 | | 7/22/2008 | | PASS |
|
|
|
plans are approved
|
Inspection Record Card- Fire | 7/22/2008 | | 7/22/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/22/2008 | | DONE |
|
|
|
|
Application received | | | 7/8/2008 | | |
Marsha Smylie
|
|
|
|
Case Summary | | | 7/8/2008 | | |
Marsha Smylie
|
|
|
|
Pending Assignment by SAM | 7/8/2008 | | | | |
Sam Rogers
|
|
|
|
Plan assigned to (SAM) | 8/14/2008 | | | | |
|
|
|
|