Miscellaneous action | | | 5/13/2010 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 6/25/2009 | 6/30/2009 | 6/30/2009 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. The forward flush passed.
|
INSP-Final Inspection | 3/4/2009 | 3/5/2009 | 3/5/2009 | A | FAIL |
Troy Cobbley
|
|
|
This permit will be ok to final when the fire alarm interconnects have been verified.
|
INSP-Sprinkler Rough-in/Hydro | 2/17/2009 | 2/18/2009 | 2/18/2009 | P | PASS |
Troy Cobbley
|
|
|
The above ground hydo test for the new east addition passed.
|
Override - Parcel Holds | 2/17/2009 | 1/1/1900 | 2/17/2009 | | |
|
|
|
sprinkler only
|
INSP-Sprinkler Rough-in/Hydro | 2/10/2009 | 2/11/2009 | 2/11/2009 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed. See city approved plans for locations of sidewalls in entrance pockets are ok to cover
|
Override - Parcel Holds | 2/10/2009 | 1/1/1900 | 2/10/2009 | | |
|
|
|
flush inspection
|
INSP-Sprinkler Rough-in | 1/27/2009 | 1/28/2009 | 1/28/2009 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the sprinkler piping on the first floor, at the entry lobby, that can be covered. It has todays date 1/28/2009.
|
Override - Parcel Holds | 1/27/2009 | 1/1/1900 | 1/27/2009 | | |
|
|
|
this for fire only
|
CHANGE STATUS TO (ISS) | | | 1/16/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Case Summary | | | 1/16/2009 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/14/2009 | | 1/14/2009 | | PASS |
Tim Frost
|
|
|
See attached comments
There are NO annotations on the plans
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/14/2009 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 1/14/2009 | | |
|
|
|
|
Inspection Record Card- Fire | 1/14/2009 | | 1/14/2009 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 1/14/2009 | | DONE |
Cathy Brown
|
|
|
tlk to tom easton ###-#### that permit and fees are ready to be picked up
|
Override - Parcel Holds | | | 1/14/2009 | | |
|
|
|
|
Permit Ready to Issue | | | 1/14/2009 | | DONE |
Cathy Brown
|
|
|
|
INSP-Sprinkler Rough-in | 1/12/2009 | 1/13/2009 | 1/13/2009 | A | PASS |
Troy Cobbley
|
|
|
The north east facing canopy can be covered.
|
Plan assigned to (SAM) | 1/12/2009 | | 1/12/2009 | | DONE |
Barbara Stitt
|
|
|
|
Plan resubmittals received | | | 1/12/2009 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 1/12/2009 | | |
|
|
|
|
INSP-Sprinkler Rough-in | 1/8/2009 | 1/9/2009 | 1/9/2009 | A | PASS |
Troy Cobbley
|
|
|
The two east side outside canopies are ok to cover.
|
Override - Parcel Holds | 1/8/2009 | 1/1/1900 | 1/8/2009 | | |
|
|
|
r/i inspection
|
INSP-Sprinkler Rough-in | 1/6/2009 | 1/6/2009 | 1/6/2009 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping in the upper level of the new east entry lobby can be covered. Plan resubmittals are required showing the piping changes. I spoke to Tom with Viking about this.
|
Override - Parcel Holds | | | 1/6/2009 | | |
|
|
|
|
INSP-Supply line flush | 12/8/2008 | 12/9/2008 | 12/9/2008 | A | PASS |
Troy Cobbley
|
|
|
This inspection was actually for an underground hydro not an underground flush. The hydro test passed.
|
Miscellaneous action | | | 11/20/2008 | | DONE |
|
|
|
Approved contractor's request to install dry sidewall (DSW) sprinklers in a cold concealed space, in excess of the maximum listed distance below the floor joists. Due to practical difficulties presented by the construction, and the relatively small area (156 sf) and shallow depth (24") of the concealed space, it will be approved to install the DSW heads with the deflectors at 8" below the floor joists." (ref. IFC 104.8)
|
INSP-Sprinkler Rough-in/Hydro | 10/10/2008 | 10/13/2008 | 10/13/2008 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans with todays date for locations where the sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 10/9/2008 | 10/9/2008 | 10/9/2008 | P | FAIL |
Forrest France
|
|
|
Trapeeze hangers at the lower level branch lines in the south office and delivery rooms are not approved (sidewinder sammys in the narrow dimention), discussed main and branchline changes to be shown on resubmittals prior to project final. See stamped plan set for location inspected today.
|
INSP-Sprinkler Rough-in | 8/21/2008 | 8/22/2008 | 8/22/2008 | P | PASS |
Troy Cobbley
|
|
|
This inspection was for the underground supply cover. The two 45 elbows have been replaced with a single 90 elbow. The piping is approved for cover.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/22/2008 | | 8/22/2008 | | DONE |
|
|
|
|
Telephone call | | | 8/22/2008 | | DONE |
|
|
|
left vm for tom easton at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 8/22/2008 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 8/22/2008 | | DONE |
Tisha Gallop
|
|
|
picked up plan mod
|
(F) Reprint permit | | | 8/22/2008 | | DONE |
Tisha Gallop
|
|
|
|
Sprinkler Plan Check | 8/13/2008 | | 8/20/2008 | | PASS |
|
|
|
plans are approved
|
Plan resubmittals received | | | 8/13/2008 | | DONE |
|
|
|
Received 5 sets of resubmittal plans stamped plans and sent to fire
|
Plan assigned to (OutSourced) | 8/11/2008 | | 8/11/2008 | | DONE |
Cathy Brown
|
|
|
|
Sprinkler Plan Check | 7/31/2008 | | 8/7/2008 | | FAIL |
|
|
|
These plans were denied do to lack of or missing information. Upon request, the denied set of plans my be retrieved from my office for salvage. The denied set of plans will be maintained for five working days
|
Plan resubmittals received | | | 7/31/2008 | | |
|
|
|
received fire spr app, united water sheet, fire spr ungrade (8) pages--"5" sets of plans- put plans on fire shelf
|
Issue and Print Permit | | | 7/28/2008 | | |
|
|
|
|
Inspection Record Card- Fire | 7/25/2008 | | 7/25/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/25/2008 | | DONE |
|
|
|
|
Telephone call | | | 7/25/2008 | | DONE |
|
|
|
left vm for tom easton at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 7/25/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/11/2008 | | 7/24/2008 | | PASS |
|
|
|
plans are approved
|
Application received | | | 7/11/2008 | | |
|
|
|
|
Pending Assignment by SAM | 7/11/2008 | | 7/11/2008 | | DONE |
Tim Frost
|
|
|
|
Case Summary | | | 7/11/2008 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 7/11/2008 | | | | |
|
|
|
|
Plan resubmittals received | | | | | |
Sam Rogers
|
|
|
|